Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

What changed in the TEC register

9,714 changes across 154 registers since 29 Jan 2021, newest first.

When a connection date moves, so does what a project is worth. Read our study: Sell now, or wait for your Gate 2 offer?

Each count is a number of changes, not projects. All changes (9,714) also includes 864 changes that fit no other category: 781 substation renamings, 28 “Not in this register”, 28 “Listed again”, 23 removed gate markings and 4 moves of connected MW between stages. No change is in more than one category.

About this history

Until October 2025, QueueWatch has one register a month, the last NESO published that month, so a change shown in those months may combine several of NESO’s updates. November 2025 has two, and from 9 December 2025 QueueWatch has NESO’s twice-weekly registers.

64 projects left the register before NESO started numbering projects in September 2023. They’re counted here but don’t have a page of their own.

Registers from 29 January 2021 to 11 August 2026 are copies NESO released to QueueQuant on 19 October 2026 under the Environmental Information Regulations 2004 (request FOI/26/226). Registers from 14 August 2026 are the ones QueueWatch downloaded from NESO’s Data Portal.

How often do connection dates move, and how many projects leave the queue? See Delays and exits in the transmission queue since 2021.

Register of 16 Nov 2026

9 changes compared with 13 Nov 2026

  • Creag DhubhNorth Scotland, Onshore windConnection date moved from 31 Oct 2030 to 31 Oct 2032 (+24 months)+24 mo
  • Creag DhubhNorth Scotland, Onshore windGiven a Gate 2 connection offerGate 2
  • Dyce Energy Storage FacilityNorth Scotland, StorageAdded to the registerNew
  • Cottered - PVDPEngland and Wales, Storage with solar or windMarked as Gate 1
  • Creag DhubhNorth Scotland, Onshore windCapacity changed from 38.3 MW to 27 MW
  • Creag DhubhNorth Scotland, Onshore windStatus changed from Scoping to Consents Approved
  • Creag Riabhach Wind FarmNorth Scotland, Onshore windStage 1: Gate marking removed (was Gate 1)
  • Edinbane WindfarmNorth Scotland, Storage with solar or windStage 1: Gate marking removed (was Gate 1)
  • PVDP ScarningEngland and Wales, Storage with solar or windMarked as Gate 1

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO