QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Where the transmission queue stands

Capacity waiting to connect in the 16 Nov 2026 register, counted at the stage and date it is due. Built capacity is excluded.

For more on the queue, see our analyses of delays and exits since 2021, Gate 2, the battery queue and CMP470, changes of customer, whether projects connect on time, which connection dates slip least, and grid outages against the connections due by 2030.

594.9 GWwaiting to connect
25.2 GWof that with Gate 2 offers
1,692projects waiting
16.9 GWpast its connection date, 100 projects

How to cite this page

You’re welcome to quote our figures, charts and findings with this credit:

QueueWatch by QueueQuant, ‘Where the transmission queue stands’, queuequant.com/queuewatch/stats/ (data to 16 November 2026). Contains data from NESO’s TEC register. Supported by National Energy SO Open Data.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO