QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Distribution / Sites / Customer

enray power ltd

Customer named in the DNOs’ registers

In UKPN’s November 2026 and NGED’s August 2026 editions

The registers spell this customer’s name more than one way: “enray power ltd” (3 sites), “Enray Power Limited” (1 site) and “enray power limited” (1 site).

5sites of 1 MW and over
217 MWcapacity
–connected (0 sites)
217 MWaccepted to connect (5 sites)

Capacity by DNO

DNOEditionSitesCapacityConnectedAccepted to connect
UKPNNovember 2026 edition112.5 MW–12.5 MW
NGEDAugust 2026 edition4204 MW–204 MW

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage3164 MW–164 MW
Solar252.5 MW–52.5 MW

Each site is grouped by its first energy source, as the register names it.

Sites

Each site under this name in the DNOs’ latest editions, the largest first.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

SiteDNOGrid supply pointTechnologyStatusMW
Woodtown farmNGEDAlverdiscott SgpStorageAccepted to connect99.4
Land lying to the southNGEDEnderby 132Kv S StnSolarAccepted to connect40
Landown farmNGEDWillington 132Kv S StnStorageAccepted to connect40
Church farmNGEDRatcliffe On Soar 132Kv S StnStorageAccepted to connect25
Ryston EstateUKPNWalpoleSolarAccepted to connect12.5

Grid supply points

Each grid supply point its sites are at, with the capacity of its own sites there.

Grid supply pointDNOSitesConnectedAccepted to connect
Alverdiscott SgpNGED1–99.4 MW
Enderby 132Kv S StnNGED1–40 MW
Willington 132Kv S StnNGED1–40 MW
Ratcliffe On Soar 132Kv S StnNGED1–25 MW
WalpoleUKPN1–12.5 MW

What changed recently

Changes to its sites found in both editions of each pair, newest first.

UKPN, October 2026 edition to November 2026 edition, for this customer’s sites: 1 site matched. Every October site and every November site had a match in the other edition.

Tracking NGED’s register since its August 2026 edition. Changes will show from its next edition.

No change to any detail QueueWatch tracks for its sites so far.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?