Distribution / Changes

What changed in the DNOs’ registers

Changes to sites found in both editions of each pair, by DNO, newest first: 1,171 changes across 57 pairs of editions.

When a connection date moves, so does what a project is worth. Read our study: Sell now, or wait for your Gate 2 offer?

UK Power Networks

UKPN’s page
Embedded Capacity Register 2 – 1MW and above, November 2026 edition. 2 pairs of editions compared.

October 2026 edition to November 2026 edition

101 changes

1,025 sites matched. 14 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.

  • ((ANM) Stow RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 27 Oct 2037 (108 months later)
  • (ANM) 68-70 Reach RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 31 Oct 2031 (36 months later)
  • (ANM) Abbotsley RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 31 Oct 2031 (36 months later)
  • (ANM) Ashwell RoadEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2024 to 30 Mar 2026 (15 months later)
  • (ANM) Beerhouse FarmEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
  • (ANM) Bracon AshEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
  • (ANM) Bunwell RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
  • (ANM) Bushmead RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 27 Oct 2037 (108 months later)
  • (ANM) ChelmsfordEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 11 Jan 2032 (36 months later)
  • (ANM) Childerley HallEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 31 Oct 2031 (36 months later)
  • (ANM) Crays Hall FarmEastern Power Networks (EPN)Target energisation date moved from 30 Jun 2025 to 10 Dec 2025 (5 months later)
  • (ANM) Crows LaneEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 11 Jan 2032 (36 months later)
  • (ANM) East Tilbury QuarryEastern Power Networks (EPN)Target energisation date moved from 30 Oct 2030 to 11 Jan 2032 (14 months later)
  • (ANM) Fallow Solar FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 31 Oct 2029 (10 months later)
  • (ANM) Green EndEastern Power Networks (EPN)Target energisation date stated as 31 Oct 2034 (not stated in the October 2026 edition)
  • (ANM) Kestrel Solar FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 31 Oct 2029 (10 months later)
  • (ANM) Kingsey Solar FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2024 to 30 Dec 2025 (12 months later)
  • (ANM) Land At Cressing FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2024 to 30 Mar 2026 (15 months later)
  • (ANM) Land At Warmans FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 31 Oct 2029 (10 months later)
  • (ANM) Land East Of Drayton LaneEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
  • (ANM) Land North Of Bassmead ManorEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 27 Oct 2037 (108 months later)
  • (ANM) Land Off Twinwood RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 27 Oct 2037 (108 months later)
  • (ANM) Land On The South East Side Of Wilsons RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 31 Oct 2031 (36 months later)
  • (ANM) Land South Of A47Eastern Power Networks (EPN)Target energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
  • (ANM) Marshes Burnham-On-CrouchEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 11 Jan 2032 (36 months later)
  • (ANM) North West Of Kimblewick RoadEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2024 to 30 Dec 2025 (12 months later)
  • (ANM) Parkgate FarmEastern Power Networks (EPN)Target energisation date moved from 6 Jan 2025 to 31 Mar 2026 (15 months later)
  • (ANM) Rowley Hill RoadEastern Power Networks (EPN)Target energisation date moved from 12 Jan 2024 to 31 Oct 2026 (34 months later)
  • (ANM) South Woodham FerrersEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 11 Jan 2032 (36 months later)
  • (ANM) SS17 9LL The ManorwayEastern Power Networks (EPN)Target energisation date moved from 30 Nov 2024 to 30 Nov 2025 (12 months later)
  • (ANM) Vicarage LaneEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 27 Oct 2037 (108 months later)
  • (ANM) Water Hall FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 31 Oct 2029 (10 months later)
  • (ANM) Weirs Drove 2Eastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 31 Oct 2031 (36 months later)
  • (ANM)Foxholes FarmEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 27 Oct 2037 (108 months later)
  • Bank Farm SolarSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Jan 2025 to 31 Dec 2028 (47 months later)
  • Bentley EstateSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2030 to 31 Dec 2031 (12 months later)
  • Berden Hall Farm PVEastern Power Networks (EPN)Target energisation date moved from 20 Jun 2025 to 31 Mar 2027 (21 months later)
  • Bockingfold FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 24 Apr 2025 to 11 Jul 2025 (3 months later)
  • Bolney SolarSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2030 to 31 Dec 2031 (12 months later)
  • Boreham StreetSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Jan 2029 to 31 Dec 2031 (35 months later)
  • Brogborough Solar FarmEastern Power Networks (EPN)Target energisation date stated as 23 Nov 2026 (not stated in the October 2026 edition)
  • Broomfield Solar FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 18 Oct 2027 to 28 Oct 2027 (10 days later)
  • Broomfield Solar FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2030 to 31 Dec 2031 (12 months later)
  • Cards RoadEastern Power Networks (EPN)Target energisation date moved from 6 Jan 2025 to 30 Mar 2026 (15 months later)
  • Chalgrave ManorEastern Power Networks (EPN)Target energisation date moved from 31 Mar 2025 to 31 Oct 2028 (43 months later)
  • Common Barn Wind Farm Phase 2Eastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 27 Oct 2037 (108 months later)
  • Coombe FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Jan 2029 to 31 Oct 2027 (15 months earlier)
  • Dereham RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
  • Discovery ParkSouth Eastern Power Networks (SPN)Target energisation date stated as 4 Jan 2026 (not stated in the October 2026 edition)
  • Envirtotech 3South Eastern Power Networks (SPN)Target energisation date moved from 31 Oct 2026 to 28 Oct 2027 (12 months later)
  • Fambridge FarmEastern Power Networks (EPN)Target energisation date moved from 6 Jan 2025 to 30 Mar 2026 (15 months later)
  • FDG F-02 Land At Chittering DroveEastern Power Networks (EPN)Target energisation date moved from 6 Jan 2025 to 30 Sep 2025 (9 months later)
  • Gabriel Spring RoadSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Jan 2025 to 31 Oct 2027 (33 months later)
  • Gatwick Airport Electric ForecourtSouth Eastern Power Networks (SPN)Target energisation date not stated (30 Sep 2024 in the October 2026 edition)
  • Great Wheatley Solar FarmEastern Power Networks (EPN)Target energisation date moved from 6 Jan 2025 to 30 Mar 2026 (15 months later)
  • Guildford STWSouth Eastern Power Networks (SPN)Target energisation date moved from 30 Apr 2025 to 10 Jul 2025 (2 months later)
  • Hale Farm, HulcottEastern Power Networks (EPN)Target energisation date moved from 30 May 2025 to 31 Oct 2028 (41 months later)
  • Halewick LaneSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2024 to 18 Dec 2026 (24 months later)
  • Highfield FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2024 to 30 Sep 2026 (21 months later)
  • Horton Wood Solar FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Oct 2025 to 20 Jun 2026 (8 months later)
  • Ironsbottom Solar FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2030 to 31 Dec 2031 (12 months later)
  • Isle Of GrainSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2024 to 31 Dec 2025 (12 months later)
  • Kentish Farm 1Eastern Power Networks (EPN)Target energisation date moved from 6 Jan 2025 to 31 Oct 2030 (70 months later)
  • Kentish Farm 2Eastern Power Networks (EPN)Target energisation date moved from 6 Jan 2025 to 31 Oct 2030 (70 months later)
  • Kingsey Solar FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2024 to 30 Apr 2026 (16 months later)
  • Kingsnorth Power StationSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2024 to 31 Oct 2026 (22 months later)
  • Knowl Green FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2024 to 31 Jul 2026 (19 months later)
  • Land At Harp FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 30 Apr 2025 to 31 Oct 2027 (30 months later)
  • Land At Priesthawes FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2030 to 31 Dec 2031 (12 months later)
  • Land At Redcoats FarmEastern Power Networks (EPN)Target energisation date moved from 28 Apr 2028 to 31 Oct 2029 (18 months later)
  • Land Near Hadham RdEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 31 Oct 2029 (10 months later)
  • Land To The North Of Sewage WorksSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2024 to 31 Oct 2026 (22 months later)
  • Little Flanchford FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2030 to 31 Dec 2031 (12 months later)
  • Lower Dunton RoadEastern Power Networks (EPN)Target energisation date not stated (30 Oct 2024 in the October 2026 edition)
  • Maggotts EndEastern Power Networks (EPN)Target energisation date moved from 12 Jan 2024 to 31 Oct 2029 (70 months later)
  • Marden GenerationSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Mar 2025 to 9 Jan 2027 (21 months later)
  • Mathurst Farm SolarSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Mar 2029 to 31 Dec 2031 (33 months later)
  • Merton CollegeSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Mar 2025 to 31 Oct 2027 (31 months later)
  • Northfleet East GridSouth Eastern Power Networks (SPN)Target energisation date moved from 30 Jun 2025 to 31 Oct 2025 (4 months later)
  • Offham QuarrySouth Eastern Power Networks (SPN)Export capacity stated as 9.5 MW (not stated in the October 2026 edition)
  • Offham QuarrySouth Eastern Power Networks (SPN)Target energisation date not stated (30 Apr 2025 in the October 2026 edition)
  • Olives FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2030 to 31 Dec 2027 (36 months earlier)
  • Ouse Valley SolarSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2030 to 31 Dec 2031 (12 months later)
  • Ph 2 Cu-Mining DagenhamEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2024 to 3 Mar 2026 (14 months later)
  • Quakers HouseEastern Power Networks (EPN)Target energisation date moved from 15 Nov 2025 to 31 Oct 2028 (36 months later)
  • Rayleigh SiteEastern Power Networks (EPN)Target energisation date moved from 6 Jan 2025 to 30 Mar 2026 (15 months later)
  • Richborough Energy ParkSouth Eastern Power Networks (SPN)Target energisation date moved from 30 Jun 2025 to 3 Jan 2026 (6 months later)
  • Rowley LaneEastern Power Networks (EPN)Target energisation date not stated (31 Oct 2033 in the October 2026 edition)
  • School LaneSouth Eastern Power Networks (SPN)Target energisation date moved from 30 Jan 2025 to 10 Jan 2026 (11 months later)
  • Shearwater Solar FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Jan 2029 to 31 Dec 2031 (35 months later)
  • Slyfield FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 1 Jan 2025 to 31 Jan 2029 (49 months later)
  • Southfleet Hook GreenSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2027 to 15 Oct 2027 (3 months earlier)
  • Tring RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2024 to 31 Oct 2028 (48 months later)
  • Vigo Lane Solar ParkSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Jan 2029 to 31 Dec 2031 (35 months later)
  • Wealden WorksSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Oct 2025 to 31 Oct 2026 (12 months later)
  • West Thaxted Solar FarmEastern Power Networks (EPN)Target energisation date moved from 12 Jan 2024 to 1 Dec 2025 (23 months later)
  • Wharf RoadEastern Power Networks (EPN)Target energisation date moved from 13 Mar 2025 to 30 Mar 2026 (13 months later)
  • Wickham HallEastern Power Networks (EPN)Target energisation date moved from 12 Jan 2024 to 1 Dec 2025 (23 months later)
  • Wickham HallEastern Power Networks (EPN)Target energisation date moved from 6 Jun 2025 to 6 Jun 2026 (12 months later)
  • Wineham LaneSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Oct 2026 to 31 Oct 2027 (12 months later)
  • Woburn RoadEastern Power Networks (EPN)Target energisation date not stated (22 Dec 2025 in the October 2026 edition)
14 sites without a match in the other edition
In the November 2026 edition only (3)
    In the October 2026 edition only (11)

      September 2026 edition to October 2026 edition

      14 changes

      1,033 sites matched. 11 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.

      • Enterprise PowerSouth Eastern Power Networks (SPN)Capacity changed from 5 MW to 5.07 MW+0.07 MW
      • Enterprise PowerSouth Eastern Power Networks (SPN)Export capacity changed from 5 MW to 5.07 MW
      • Francis WoodSouth Eastern Power Networks (SPN)Capacity changed from 4.4 MW to 7 MW+2.6 MW
      • Francis WoodSouth Eastern Power Networks (SPN)Export capacity changed from 4.4 MW to 7 MW
      • Lower Dunton RoadEastern Power Networks (EPN)Customer changed from Conrad Energy Limited to Conrad (Lower Dunton) Limited
      • Olives FarmSouth Eastern Power Networks (SPN)Capacity changed from 75 MW to 49.9 MW−25.1 MW
      • Olives FarmSouth Eastern Power Networks (SPN)Export capacity changed from 75 MW to 49.9 MW
      • PV Solar (Carlton Farm)Eastern Power Networks (EPN)Capacity changed from 5.5 MW to 5 MW−0.5 MW
      • PV Solar (Carlton Farm)Eastern Power Networks (EPN)Export capacity changed from 5.5 MW to 5 MW
      • Tilbury Docks Ph2Eastern Power Networks (EPN)Capacity changed from 20 MW to 40 MW+20 MW
      • Tilbury Docks Ph2Eastern Power Networks (EPN)Customer changed from ESB International to Thameside Energy Recovery Facility Limited 2021
      • Tilbury Docks Ph2Eastern Power Networks (EPN)Export capacity changed from 20 MW to 40 MW
      • Westgate PowerSouth Eastern Power Networks (SPN)Capacity changed from 5.34 MW to 5.33 MW−0.01 MW
      • Westgate PowerSouth Eastern Power Networks (SPN)Export capacity changed from 5.34 MW to 5.33 MW
      11 sites without a match in the other edition
      In the October 2026 edition only (3)
        In the September 2026 edition only (8)

          National Grid Electricity Distribution

          NGED’s page

          Tracking NGED’s register since its August 2026 edition. Changes will show from its next edition.

          Scottish and Southern Electricity Networks

          SSEN’s page
          Embedded Capacity Register, November 2026 edition. 39 pairs of editions compared.

          October 2026 edition to November 2026 edition

          37 changes

          1,290 sites matched. 19 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.

          19 sites without a match in the other edition
          In the November 2026 edition only (8)
            In the October 2026 edition only (11)

              September 2026 edition to October 2026 edition

              33 changes

              1,291 sites matched. 20 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.

              20 sites without a match in the other edition
              In the October 2026 edition only (10)
                In the September 2026 edition only (10)

                  August 2026 edition to September 2026 edition

                  43 changes

                  1,293 sites matched. 20 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.

                  20 sites without a match in the other edition
                  In the September 2026 edition only (8)
                    In the August 2026 edition only (12)

                      SP Energy Networks

                      SPEN’s page
                      Embedded Capacity Register >1MW, September 2026 edition. 6 pairs of editions compared.

                      August 2026 edition to September 2026 edition

                      35 changes

                      773 sites matched. 2 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.

                      • AGS Calderside Farm SolarCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
                      • AGS Calderside Farm SolarCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
                      • Ardoch Farm BESS (Kilwinning BESS)Central and Southern Scotland (SPD)Target energisation date moved from 30 Aug 2027 to 30 Jul 2027 (1 month earlier)
                      • Benthead Farm Solar and BESSCentral and Southern Scotland (SPD)Capacity changed from 70.4 MW to 113.43 MW+43.03 MW
                      • Benthead Farm Solar and BESSCentral and Southern Scotland (SPD)Target energisation date moved from 18 Sep 2026 to 1 Oct 2026 (13 days later)
                      • Burnbank Coatbridge BESSCentral and Southern Scotland (SPD)In a connection queue changed from “no” to “yes”
                      • Dalmarnock Road BESS (Former Sanmex Site)Central and Southern Scotland (SPD)Target energisation date moved from 1 Sep 2026 to 11 Sep 2026 (10 days later)
                      • Dewshill Wind FarmCentral and Southern Scotland (SPD)Target energisation date moved from 3 Aug 2027 to 3 Sep 2027 (1 month later)
                      • Doveryard (Oldhall ERF)Central and Southern Scotland (SPD)Target energisation date moved from 29 Aug 2026 to 4 Sep 2026 (6 days later)
                      • Drumfad Battery Storage SystemCentral and Southern Scotland (SPD)Target energisation date moved from 31 Oct 2027 to 30 Oct 2027 (1 day earlier)
                      • Elderslie EstateCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
                      • Elderslie EstateCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
                      • Energy Park FifeCentral and Southern Scotland (SPD)Target energisation date moved from 30 Oct 2028 to 30 Oct 2029 (12 months later)
                      • Greenside FarmCentral and Southern Scotland (SPD)Target energisation date moved from 20 Nov 2027 to 28 Mar 2028 (4 months later)
                      • Holmston Farm (Previously Broomfield Lodge)Central and Southern Scotland (SPD)Target energisation date moved from 26 Aug 2026 to 21 Sep 2026 (1 month later)
                      • Inverkeithing Solar FarmCentral and Southern Scotland (SPD)Target energisation date stated as 31 Mar 2031 (not stated in the August 2026 edition)
                      • Kirknewton Solar & BESSCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
                      • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Capacity changed from 2.25 MW to 2.175 MW−0.075 MW
                      • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 2.25 MW to 2.175 MW
                      • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “no” to “yes”
                      • Lesmahagow WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
                      • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
                      • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Target energisation date not stated (31 Oct 2028 in the August 2026 edition)
                      • Lochfauld Solar ParkCentral and Southern Scotland (SPD)Target energisation date moved from 30 Aug 2026 to 9 Oct 2026 (1 month later)
                      • South Clyde Energy CentreCentral and Southern Scotland (SPD)Target energisation date moved from 13 Aug 2026 to 20 Sep 2026 (1 month later)
                      • Steven's Croft BiomassCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
                      • Strathaven West 69.8MWCentral and Southern Scotland (SPD)Target energisation date moved from 1 Jul 2029 to 31 Oct 2030 (16 months later)
                      • Thermo Fisher Inchinnan Solar GeneratorCentral and Southern Scotland (SPD)Target energisation date moved from 31 Oct 2029 to 31 Aug 2029 (2 months earlier)
                      • Thermo Fisher Inchinnan Solar Generator Alternative FeedCentral and Southern Scotland (SPD)Target energisation date moved from 31 Oct 2029 to 31 Aug 2029 (2 months earlier)
                      • Touch Energy ParkCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
                      • Westfield SolarCentral and Southern Scotland (SPD)Target energisation date moved from 28 Jan 2028 to 28 Apr 2028 (3 months later)
                      • Woodlands Farm WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “no” to “yes”
                      • Woodlands Farm WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
                      • Woodlands Farm WindfarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
                      • Woodlands Farm WindfarmCentral and Southern Scotland (SPD)Target energisation date not stated (31 Oct 2028 in the August 2026 edition)
                      2 sites without a match in the other edition
                      In the August 2026 edition only (2)

                        July 2026 edition to August 2026 edition

                        56 changes

                        768 sites matched. 8 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.

                        • Andershaw WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
                        • Andershaw WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “no” to “yes”
                        • Andershaw WindfarmCentral and Southern Scotland (SPD)Status changed from “connected” to “accepted to connect”
                        • Andershaw WindfarmCentral and Southern Scotland (SPD)Target energisation date stated as 31 Oct 2028 (not stated in the July 2026 edition)
                        • Ardoch Farm BESS (Kilwinning BESS)Central and Southern Scotland (SPD)Target energisation date moved from 30 Apr 2027 to 30 Aug 2027 (4 months later)
                        • Benthead Farm Solar and BESSCentral and Southern Scotland (SPD)Target energisation date moved from 13 Aug 2026 to 18 Sep 2026 (1 month later)
                        • Bentley MotorsMerseyside, Cheshire and North Wales (SPM)Customer changed from Bentley Motors to QuiNotas ENoergy UK
                        • Bentley MotorsMerseyside, Cheshire and North Wales (SPM)Status changed from “connected” to “accepted to connect”
                        • Doveryard (Oldhall ERF)Central and Southern Scotland (SPD)Target energisation date moved from 27 Jul 2026 to 29 Aug 2026 (1 month later)
                        • Getrag(Ford)Merseyside, Cheshire and North Wales (SPM)Technology changed from Solar to Gas and other fossil
                        • Gladsmuir Wind FarmCentral and Southern Scotland (SPD)Capacity changed from 43.4 MW to 31 MW−12.4 MW
                        • Gladsmuir Wind FarmCentral and Southern Scotland (SPD)Export capacity changed from 41.5 MW to 31 MW
                        • Glenniston Solar and BESSCentral and Southern Scotland (SPD)Target energisation date moved from 3 Aug 2027 to 19 Jul 2028 (12 months later)
                        • Glenrothes BESSCentral and Southern Scotland (SPD)Target energisation date moved from 30 Jun 2027 to 30 Sep 2027 (3 months later)
                        • Greengairs East WindfarmCentral and Southern Scotland (SPD)Capacity changed from 36 MW to 24 MW−12 MW
                        • Greengairs East WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 36 MW to 24 MW
                        • Heights Wind FarmCentral and Southern Scotland (SPD)Target energisation date moved from 30 Jun 2028 to 30 Aug 2028 (2 months later)
                        • Holmston Farm (Previously Broomfield Lodge)Central and Southern Scotland (SPD)Target energisation date moved from 24 Aug 2026 to 26 Aug 2026 (2 days later)
                        • Howpark WindfarmCentral and Southern Scotland (SPD)Capacity changed from 18.8 MW to 16 MW−2.8 MW
                        • Howpark WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 18.8 MW to 16 MW
                        • JAGUAR LANDROVERMerseyside, Cheshire and North Wales (SPM)Capacity changed from 15.4 MW to 17.11 MW+1.71 MW
                        • JAGUAR LANDROVERMerseyside, Cheshire and North Wales (SPM)Export capacity changed from 0.999 MW to 4.95 MW
                        • JAGUAR LANDROVERMerseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
                        • KronospanMerseyside, Cheshire and North Wales (SPM)Customer changed from River Island to Kronospan Limited
                        • KronospanMerseyside, Cheshire and North Wales (SPM)Export capacity changed from 47.4 MW to 28 MW
                        • KronospanMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “yes” to “no”
                        • KronospanMerseyside, Cheshire and North Wales (SPM)Status changed from “accepted to connect” to “connected”Connected
                        • KronospanMerseyside, Cheshire and North Wales (SPM)Technology changed from Solar to Gas and other fossil
                        • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Capacity changed from 2.175 MW to 2.25 MW+0.075 MW
                        • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 2.175 MW to 2.25 MW
                        • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
                        • Lesmahagow WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “no” to “yes”
                        • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Status changed from “connected” to “accepted to connect”
                        • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Target energisation date stated as 31 Oct 2028 (not stated in the July 2026 edition)
                        • Lochfauld Solar ParkCentral and Southern Scotland (SPD)Target energisation date moved from 30 Jul 2026 to 30 Aug 2026 (1 month later)
                        • Longhill Burn WindfarmCentral and Southern Scotland (SPD)Capacity changed from 36 MW to 50 MW+14 MW
                        • Longhill Burn WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 36 MW to 50 MW
                        • McQuittiston FarmCentral and Southern Scotland (SPD)Target energisation date moved from 29 Oct 2027 to 10 Dec 2027 (1 month later)
                        • Mill Rig WindfarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
                        • Mill Rig WindfarmCentral and Southern Scotland (SPD)Target energisation date not stated (15 Jul 2026 in the July 2026 edition)
                        • Moor FarmMerseyside, Cheshire and North Wales (SPM)Customer changed from SPF Moorfarm Ltd to G59 Projects
                        • Nether FarmCentral and Southern Scotland (SPD)Target energisation date moved from 30 Jun 2027 to 30 Sep 2027 (3 months later)
                        • Nutberry Wind FarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
                        • Nutberry Wind FarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
                        • Nutberry Wind FarmCentral and Southern Scotland (SPD)Target energisation date not stated (31 Oct 2028 in the July 2026 edition)
                        • Rogerton Cottage (Rogerton Avenue BESS)Central and Southern Scotland (SPD)Target energisation date moved from 1 Jul 2027 to 16 Aug 2027 (1 month later)
                        • Sorbie WindfarmCentral and Southern Scotland (SPD)Capacity changed from 7.5 MW to 12 MW+4.5 MW
                        • Sorbie WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 7.5 MW to 12.6 MW
                        • South Clyde Energy CentreCentral and Southern Scotland (SPD)Target energisation date moved from 14 Jul 2026 to 13 Aug 2026 (1 month later)
                        • St Marys Isle Solar FarmCentral and Southern Scotland (SPD)Target energisation date moved from 27 Jan 2030 to 27 Jun 2030 (5 months later)
                        • ToyotaMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “no” to “yes”
                        • ToyotaMerseyside, Cheshire and North Wales (SPM)Status changed from “connected” to “accepted to connect”
                        • ToyotaMerseyside, Cheshire and North Wales (SPM)Technology changed from Solar to Gas and other fossil
                        • Westfield SolarCentral and Southern Scotland (SPD)Target energisation date moved from 28 Apr 2028 to 28 Jan 2028 (3 months earlier)
                        • Wull Muir Wind FarmCentral and Southern Scotland (SPD)Flexible connection changed from “no” to “yes”
                        • Wull Muir Wind FarmCentral and Southern Scotland (SPD)In a connection queue changed from “no” to “yes”
                        8 sites without a match in the other edition
                        In the August 2026 edition only (7)
                          In the July 2026 edition only (1)

                            June 2026 edition to July 2026 edition

                            51 changes

                            766 sites matched. 18 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.

                            • Aberangell FarmMerseyside, Cheshire and North Wales (SPM)Technology changed from Wind to Solar
                            • Airies WindfarmCentral and Southern Scotland (SPD)Capacity changed from 36.7 MW to 39.9 MW+3.2 MW
                            • Andershaw WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “no” to “yes”
                            • Andershaw WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
                            • Andershaw WindfarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
                            • Andershaw WindfarmCentral and Southern Scotland (SPD)Target energisation date not stated (31 Oct 2028 in the June 2026 edition)
                            • Ardgowan EstateCentral and Southern Scotland (SPD)Capacity changed from 49.86 MW to 23.75 MW−26.11 MW
                            • Ardgowan EstateCentral and Southern Scotland (SPD)Export capacity changed from 49.9 MW to 20 MW
                            • Arran ViewCentral and Southern Scotland (SPD)Capacity changed from 40 MW to 50 MW+10 MW
                            • Arran ViewCentral and Southern Scotland (SPD)Export capacity changed from 20 MW to 49.9 MW
                            • Bentley MotorsMerseyside, Cheshire and North Wales (SPM)Capacity changed from 8 MW to 14.1 MW+6.1 MW
                            • Diageo SolarCentral and Southern Scotland (SPD)Capacity changed from 4.1 MW to 3.395 MW−0.705 MW
                            • Garviland Wind FarmCentral and Southern Scotland (SPD)Capacity changed from 24 MW to 13.5 MW−10.5 MW
                            • Garviland Wind FarmCentral and Southern Scotland (SPD)Export capacity changed from 21.3 MW to 12.5 MW
                            • Getrag(Ford)Merseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
                            • Greengairs East WindfarmCentral and Southern Scotland (SPD)Capacity changed from 24 MW to 36 MW+12 MW
                            • Greengairs East WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 24 MW to 36 MW
                            • IcelandMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “no” to “yes”
                            • IcelandMerseyside, Cheshire and North Wales (SPM)Status changed from “connected” to “accepted to connect”
                            • IcelandMerseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
                            • JAGUAR LANDROVERMerseyside, Cheshire and North Wales (SPM)Technology changed from Solar to Gas and other fossil
                            • KronospanMerseyside, Cheshire and North Wales (SPM)Capacity changed from 47.4 MW to 28 MW−19.4 MW
                            • KronospanMerseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
                            • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Capacity changed from 2.25 MW to 2.175 MW−0.075 MW
                            • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 2.25 MW to 2.175 MW
                            • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “no” to “yes”
                            • Lesmahagow WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
                            • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
                            • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Target energisation date not stated (31 Oct 2028 in the June 2026 edition)
                            • Longhill Burn WindfarmCentral and Southern Scotland (SPD)Capacity changed from 50 MW to 36 MW−14 MW
                            • Longhill Burn WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 50 MW to 36 MW
                            • Nutberry Wind FarmCentral and Southern Scotland (SPD)In a connection queue changed from “no” to “yes”
                            • Nutberry Wind FarmCentral and Southern Scotland (SPD)Status changed from “connected” to “accepted to connect”
                            • Nutberry Wind FarmCentral and Southern Scotland (SPD)Target energisation date stated as 31 Oct 2028 (not stated in the June 2026 edition)
                            • Rolls RoyceMerseyside, Cheshire and North Wales (SPM)Capacity changed from 17.015 MW to 7.1 MW−9.915 MW
                            • Rolls RoyceMerseyside, Cheshire and North Wales (SPM)Export capacity changed from 17.015 MW to 7.1 MW
                            • Shin Etsu CHPCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
                            • Shin Etsu CHPCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
                            • Shin Etsu CHPCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
                            • Shin Etsu CHPCentral and Southern Scotland (SPD)Target energisation date not stated (31 Dec 2025 in the June 2026 edition)
                            • Sorbie WindfarmCentral and Southern Scotland (SPD)Capacity changed from 12 MW to 7.5 MW−4.5 MW
                            • Sorbie WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 12.6 MW to 7.5 MW
                            • Stanwardine Grange PV & BESSMerseyside, Cheshire and North Wales (SPM)Technology changed from Storage to Solar
                            • Touch Energy ParkCentral and Southern Scotland (SPD)Capacity changed from 71.4 MW to 54 MW−17.4 MW
                            • ToyotaMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “yes” to “no”
                            • ToyotaMerseyside, Cheshire and North Wales (SPM)Status changed from “accepted to connect” to “connected”Connected
                            • ToyotaMerseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
                            • Williams Farm Solar (Phase 2)Merseyside, Cheshire and North Wales (SPM)Capacity changed from 16.27 MW to 10 MW−6.27 MW
                            • Williams Farm Solar (Phase 2)Merseyside, Cheshire and North Wales (SPM)Customer changed from Renewabuild to Solar Ventures
                            • Williams Farm Solar (Phase 2)Merseyside, Cheshire and North Wales (SPM)Technology changed from Storage to Solar
                            • Wull Muir Wind FarmCentral and Southern Scotland (SPD)Target energisation date not stated (1 Oct 2029 in the June 2026 edition)
                            18 sites without a match in the other edition
                            In the July 2026 edition only (3)
                              In the June 2026 edition only (15)

                                Northern Powergrid

                                Northern Powergrid’s page
                                Embedded Capacity Register 1MW and Over, November 2026 edition. 8 pairs of editions compared.

                                October 2026 edition to November 2026 edition

                                No changes found.

                                933 sites matched. 5 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.

                                5 sites without a match in the other edition
                                In the November 2026 edition only (4)
                                  In the October 2026 edition only (1)

                                    September 2026 edition to October 2026 edition

                                    6 changes

                                    929 sites matched. 7 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.

                                    • Knapton HybridNorth East (Northern Powergrid)Export capacity changed from 114 MW to 41.5 MW
                                    • Knapton HybridNorth East (Northern Powergrid)Status changed from “accepted to connect” to “connected”Connected
                                    • Station Road CHPNorth East (Northern Powergrid)Capacity changed from 3.8 MW to 4.7 MW+0.9 MW
                                    • Station Road CHPNorth East (Northern Powergrid)Customer changed from Jan Bezemer And Sons Ltd to Station Road CHP
                                    • Station Road CHPNorth East (Northern Powergrid)Export capacity changed from 3.8 MW to 4.7 MW
                                    • Station Road CHPNorth East (Northern Powergrid)Status changed from “connected” to “accepted to connect”
                                    7 sites without a match in the other edition
                                    In the October 2026 edition only (5)
                                      In the September 2026 edition only (2)

                                        August 2026 edition to September 2026 edition

                                        1 change

                                        928 sites matched. 12 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.

                                        • Western School PVYorkshire (Northern Powergrid)Status changed from “accepted to connect” to “connected”Connected
                                        12 sites without a match in the other edition
                                        In the September 2026 edition only (3)
                                          In the August 2026 edition only (9)

                                            Electricity North West

                                            ENWL’s page
                                            Embedded Capacity Register 2 – 1MW and above, October 2026 edition. 2 pairs of editions compared.

                                            September 2026 edition to October 2026 edition

                                            No changes found.

                                            561 sites matched. Every September site and every October site had a match in the other edition.

                                            May 2026 edition to September 2026 edition

                                            3 changes

                                            559 sites matched. 7 sites couldn’t be matched between the two editions, because their details changed or they appear in only one. QueueWatch holds no edition between these two (4 months apart). ENWL’s May 2026 edition: its rows were last updated on 22 June 2026.

                                            • BARROW FLOATING SOLARNorth West England (ENWL)Capacity changed from 0 MW to 11 MW+11 MW
                                            • SOWERBY LODGE FARMNorth West England (ENWL)Capacity stated as 38 MW (not stated in the May 2026 edition)
                                            • WHITWORTHNorth West England (ENWL)Capacity stated as 5 MW (not stated in the May 2026 edition)
                                            7 sites without a match in the other edition
                                            In the September 2026 edition only (2)
                                              In the May 2026 edition only (5)
                                                QueueQuant

                                                Price what a delay would do to your project

                                                QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

                                                Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

                                                Price my project

                                                Get the plan that holds up best for your site, and where that answer flips.

                                                What you get from QueueQuant

                                                • The route to power that wins
                                                • How to size every asset on the site
                                                • The level of delay or curtailment at which that answer flips
                                                • Whether the project is worth building at all
                                                • How bad the worst outcomes get, at the risk level you choose

                                                See how we’d price it: Sell now, or wait for your Gate 2 offer?