SP Energy Networks

Embedded Capacity Register >1MW, September 2026 edition

773sites of 1 MW and over
17.1 GWcapacity
6.3 GWconnected (483 sites)
10.8 GWaccepted to connect (290 sites)

Capacity by edition month

Total capacity of sites of 1 MW and over, month by month, from SPEN’s own files only.

0 GW5 GW10 GW15 GW20 GWMar 2026March 2026: 6.2 GW connected, 10.5 GW accepted to connect (SPEN’s own edition)April 2026: 6.3 GW connected, 10.4 GW accepted to connect (SPEN’s own edition)May 2026: 6.2 GW connected, 10.5 GW accepted to connect (SPEN’s own edition)June 2026: 6.2 GW connected, 11.3 GW accepted to connect (SPEN’s own edition)July 2026: 6.2 GW connected, 10.8 GW accepted to connect (SPEN’s own edition)August 2026: 6.3 GW connected, 10.8 GW accepted to connect (SPEN’s own edition)September 2026: 6.3 GW connected, 10.8 GW accepted to connect (SPEN’s own edition)

ConnectedAccepted to connectSPEN’s own edition

The figures, month by month
Edition monthSourceSitesConnectedAccepted to connectTotal
September 2026SPEN’s own edition7736.3 GW10.8 GW17.1 GW
August 2026SPEN’s own edition7756.3 GW10.8 GW17.1 GW
July 2026SPEN’s own edition7696.2 GW10.8 GW17.0 GW
June 2026SPEN’s own edition7816.2 GW11.3 GW17.5 GW
May 2026SPEN’s own edition7666.2 GW10.5 GW16.7 GW
April 2026SPEN’s own edition7666.3 GW10.4 GW16.7 GW
March 2026SPEN’s own edition7676.2 GW10.5 GW16.7 GW

What changed between editions

Changes to sites found in both editions of each pair, newest first.

August 2026 edition to September 2026 edition 35 changes

773 sites matched. 2 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.

  • AGS Calderside Farm SolarCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
  • AGS Calderside Farm SolarCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
  • Ardoch Farm BESS (Kilwinning BESS)Central and Southern Scotland (SPD)Target energisation date moved from 30 Aug 2027 to 30 Jul 2027 (1 month earlier)
  • Benthead Farm Solar and BESSCentral and Southern Scotland (SPD)Capacity changed from 70.4 MW to 113.43 MW
  • Benthead Farm Solar and BESSCentral and Southern Scotland (SPD)Target energisation date moved from 18 Sep 2026 to 1 Oct 2026 (13 days later)
  • Burnbank Coatbridge BESSCentral and Southern Scotland (SPD)In a connection queue changed from “no” to “yes”
  • Dalmarnock Road BESS (Former Sanmex Site)Central and Southern Scotland (SPD)Target energisation date moved from 1 Sep 2026 to 11 Sep 2026 (10 days later)
  • Dewshill Wind FarmCentral and Southern Scotland (SPD)Target energisation date moved from 3 Aug 2027 to 3 Sep 2027 (1 month later)
  • Doveryard (Oldhall ERF)Central and Southern Scotland (SPD)Target energisation date moved from 29 Aug 2026 to 4 Sep 2026 (6 days later)
  • Drumfad Battery Storage SystemCentral and Southern Scotland (SPD)Target energisation date moved from 31 Oct 2027 to 30 Oct 2027 (1 day earlier)
  • Elderslie EstateCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
  • Elderslie EstateCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
  • Energy Park FifeCentral and Southern Scotland (SPD)Target energisation date moved from 30 Oct 2028 to 30 Oct 2029 (12 months later)
  • Greenside FarmCentral and Southern Scotland (SPD)Target energisation date moved from 20 Nov 2027 to 28 Mar 2028 (4 months later)
  • Holmston Farm (Previously Broomfield Lodge)Central and Southern Scotland (SPD)Target energisation date moved from 26 Aug 2026 to 21 Sep 2026 (1 month later)
  • Inverkeithing Solar FarmCentral and Southern Scotland (SPD)Target energisation date stated as 31 Mar 2031 (not stated in the August 2026 edition)
  • Kirknewton Solar & BESSCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
  • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Capacity changed from 2.25 MW to 2.175 MW
  • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 2.25 MW to 2.175 MW
  • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “no” to “yes”
  • Lesmahagow WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
  • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”
  • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Target energisation date not stated (31 Oct 2028 in the August 2026 edition)
  • Lochfauld Solar ParkCentral and Southern Scotland (SPD)Target energisation date moved from 30 Aug 2026 to 9 Oct 2026 (1 month later)
  • South Clyde Energy CentreCentral and Southern Scotland (SPD)Target energisation date moved from 13 Aug 2026 to 20 Sep 2026 (1 month later)
  • Steven's Croft BiomassCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
  • Strathaven West 69.8MWCentral and Southern Scotland (SPD)Target energisation date moved from 1 Jul 2029 to 31 Oct 2030 (16 months later)
  • Thermo Fisher Inchinnan Solar GeneratorCentral and Southern Scotland (SPD)Target energisation date moved from 31 Oct 2029 to 31 Aug 2029 (2 months earlier)
  • Thermo Fisher Inchinnan Solar Generator Alternative FeedCentral and Southern Scotland (SPD)Target energisation date moved from 31 Oct 2029 to 31 Aug 2029 (2 months earlier)
  • Touch Energy ParkCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
  • Westfield SolarCentral and Southern Scotland (SPD)Target energisation date moved from 28 Jan 2028 to 28 Apr 2028 (3 months later)
  • Woodlands Farm WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “no” to “yes”
  • Woodlands Farm WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
  • Woodlands Farm WindfarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”
  • Woodlands Farm WindfarmCentral and Southern Scotland (SPD)Target energisation date not stated (31 Oct 2028 in the August 2026 edition)
2 sites without a match in the other edition
In the August 2026 edition only (2)
    July 2026 edition to August 2026 edition 56 changes

    768 sites matched. 8 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.

    • Andershaw WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
    • Andershaw WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “no” to “yes”
    • Andershaw WindfarmCentral and Southern Scotland (SPD)Status changed from “connected” to “accepted to connect”
    • Andershaw WindfarmCentral and Southern Scotland (SPD)Target energisation date stated as 31 Oct 2028 (not stated in the July 2026 edition)
    • Ardoch Farm BESS (Kilwinning BESS)Central and Southern Scotland (SPD)Target energisation date moved from 30 Apr 2027 to 30 Aug 2027 (4 months later)
    • Benthead Farm Solar and BESSCentral and Southern Scotland (SPD)Target energisation date moved from 13 Aug 2026 to 18 Sep 2026 (1 month later)
    • Bentley MotorsMerseyside, Cheshire and North Wales (SPM)Customer changed from Bentley Motors to QuiNotas ENoergy UK
    • Bentley MotorsMerseyside, Cheshire and North Wales (SPM)Status changed from “connected” to “accepted to connect”
    • Doveryard (Oldhall ERF)Central and Southern Scotland (SPD)Target energisation date moved from 27 Jul 2026 to 29 Aug 2026 (1 month later)
    • Getrag(Ford)Merseyside, Cheshire and North Wales (SPM)Technology changed from Solar to Gas and other fossil
    • Gladsmuir Wind FarmCentral and Southern Scotland (SPD)Capacity changed from 43.4 MW to 31 MW
    • Gladsmuir Wind FarmCentral and Southern Scotland (SPD)Export capacity changed from 41.5 MW to 31 MW
    • Glenniston Solar and BESSCentral and Southern Scotland (SPD)Target energisation date moved from 3 Aug 2027 to 19 Jul 2028 (12 months later)
    • Glenrothes BESSCentral and Southern Scotland (SPD)Target energisation date moved from 30 Jun 2027 to 30 Sep 2027 (3 months later)
    • Greengairs East WindfarmCentral and Southern Scotland (SPD)Capacity changed from 36 MW to 24 MW
    • Greengairs East WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 36 MW to 24 MW
    • Heights Wind FarmCentral and Southern Scotland (SPD)Target energisation date moved from 30 Jun 2028 to 30 Aug 2028 (2 months later)
    • Holmston Farm (Previously Broomfield Lodge)Central and Southern Scotland (SPD)Target energisation date moved from 24 Aug 2026 to 26 Aug 2026 (2 days later)
    • Howpark WindfarmCentral and Southern Scotland (SPD)Capacity changed from 18.8 MW to 16 MW
    • Howpark WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 18.8 MW to 16 MW
    • JAGUAR LANDROVERMerseyside, Cheshire and North Wales (SPM)Capacity changed from 15.4 MW to 17.11 MW
    • JAGUAR LANDROVERMerseyside, Cheshire and North Wales (SPM)Export capacity changed from 0.999 MW to 4.95 MW
    • JAGUAR LANDROVERMerseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
    • KronospanMerseyside, Cheshire and North Wales (SPM)Customer changed from River Island to Kronospan Limited
    • KronospanMerseyside, Cheshire and North Wales (SPM)Export capacity changed from 47.4 MW to 28 MW
    • KronospanMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “yes” to “no”
    • KronospanMerseyside, Cheshire and North Wales (SPM)Status changed from “accepted to connect” to “connected”
    • KronospanMerseyside, Cheshire and North Wales (SPM)Technology changed from Solar to Gas and other fossil
    • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Capacity changed from 2.175 MW to 2.25 MW
    • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 2.175 MW to 2.25 MW
    • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
    • Lesmahagow WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “no” to “yes”
    • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Status changed from “connected” to “accepted to connect”
    • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Target energisation date stated as 31 Oct 2028 (not stated in the July 2026 edition)
    • Lochfauld Solar ParkCentral and Southern Scotland (SPD)Target energisation date moved from 30 Jul 2026 to 30 Aug 2026 (1 month later)
    • Longhill Burn WindfarmCentral and Southern Scotland (SPD)Capacity changed from 36 MW to 50 MW
    • Longhill Burn WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 36 MW to 50 MW
    • McQuittiston FarmCentral and Southern Scotland (SPD)Target energisation date moved from 29 Oct 2027 to 10 Dec 2027 (1 month later)
    • Mill Rig WindfarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”
    • Mill Rig WindfarmCentral and Southern Scotland (SPD)Target energisation date not stated (15 Jul 2026 in the July 2026 edition)
    • Moor FarmMerseyside, Cheshire and North Wales (SPM)Customer changed from SPF Moorfarm Ltd to G59 Projects
    • Nether FarmCentral and Southern Scotland (SPD)Target energisation date moved from 30 Jun 2027 to 30 Sep 2027 (3 months later)
    • Nutberry Wind FarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
    • Nutberry Wind FarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”
    • Nutberry Wind FarmCentral and Southern Scotland (SPD)Target energisation date not stated (31 Oct 2028 in the July 2026 edition)
    • Rogerton Cottage (Rogerton Avenue BESS)Central and Southern Scotland (SPD)Target energisation date moved from 1 Jul 2027 to 16 Aug 2027 (1 month later)
    • Sorbie WindfarmCentral and Southern Scotland (SPD)Capacity changed from 7.5 MW to 12 MW
    • Sorbie WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 7.5 MW to 12.6 MW
    • South Clyde Energy CentreCentral and Southern Scotland (SPD)Target energisation date moved from 14 Jul 2026 to 13 Aug 2026 (1 month later)
    • St Marys Isle Solar FarmCentral and Southern Scotland (SPD)Target energisation date moved from 27 Jan 2030 to 27 Jun 2030 (5 months later)
    • ToyotaMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “no” to “yes”
    • ToyotaMerseyside, Cheshire and North Wales (SPM)Status changed from “connected” to “accepted to connect”
    • ToyotaMerseyside, Cheshire and North Wales (SPM)Technology changed from Solar to Gas and other fossil
    • Westfield SolarCentral and Southern Scotland (SPD)Target energisation date moved from 28 Apr 2028 to 28 Jan 2028 (3 months earlier)
    • Wull Muir Wind FarmCentral and Southern Scotland (SPD)Flexible connection changed from “no” to “yes”
    • Wull Muir Wind FarmCentral and Southern Scotland (SPD)In a connection queue changed from “no” to “yes”
    8 sites without a match in the other edition
    In the August 2026 edition only (7)
      In the July 2026 edition only (1)
        June 2026 edition to July 2026 edition 51 changes

        766 sites matched. 18 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.

        • Aberangell FarmMerseyside, Cheshire and North Wales (SPM)Technology changed from Wind to Solar
        • Airies WindfarmCentral and Southern Scotland (SPD)Capacity changed from 36.7 MW to 39.9 MW
        • Andershaw WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “no” to “yes”
        • Andershaw WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
        • Andershaw WindfarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”
        • Andershaw WindfarmCentral and Southern Scotland (SPD)Target energisation date not stated (31 Oct 2028 in the June 2026 edition)
        • Ardgowan EstateCentral and Southern Scotland (SPD)Capacity changed from 49.86 MW to 23.75 MW
        • Ardgowan EstateCentral and Southern Scotland (SPD)Export capacity changed from 49.9 MW to 20 MW
        • Arran ViewCentral and Southern Scotland (SPD)Capacity changed from 40 MW to 50 MW
        • Arran ViewCentral and Southern Scotland (SPD)Export capacity changed from 20 MW to 49.9 MW
        • Bentley MotorsMerseyside, Cheshire and North Wales (SPM)Capacity changed from 8 MW to 14.1 MW
        • Diageo SolarCentral and Southern Scotland (SPD)Capacity changed from 4.1 MW to 3.395 MW
        • Garviland Wind FarmCentral and Southern Scotland (SPD)Capacity changed from 24 MW to 13.5 MW
        • Garviland Wind FarmCentral and Southern Scotland (SPD)Export capacity changed from 21.3 MW to 12.5 MW
        • Getrag(Ford)Merseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
        • Greengairs East WindfarmCentral and Southern Scotland (SPD)Capacity changed from 24 MW to 36 MW
        • Greengairs East WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 24 MW to 36 MW
        • IcelandMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “no” to “yes”
        • IcelandMerseyside, Cheshire and North Wales (SPM)Status changed from “connected” to “accepted to connect”
        • IcelandMerseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
        • JAGUAR LANDROVERMerseyside, Cheshire and North Wales (SPM)Technology changed from Solar to Gas and other fossil
        • KronospanMerseyside, Cheshire and North Wales (SPM)Capacity changed from 47.4 MW to 28 MW
        • KronospanMerseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
        • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Capacity changed from 2.25 MW to 2.175 MW
        • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 2.25 MW to 2.175 MW
        • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “no” to “yes”
        • Lesmahagow WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
        • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”
        • Lesmahagow WindfarmCentral and Southern Scotland (SPD)Target energisation date not stated (31 Oct 2028 in the June 2026 edition)
        • Longhill Burn WindfarmCentral and Southern Scotland (SPD)Capacity changed from 50 MW to 36 MW
        • Longhill Burn WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 50 MW to 36 MW
        • Nutberry Wind FarmCentral and Southern Scotland (SPD)In a connection queue changed from “no” to “yes”
        • Nutberry Wind FarmCentral and Southern Scotland (SPD)Status changed from “connected” to “accepted to connect”
        • Nutberry Wind FarmCentral and Southern Scotland (SPD)Target energisation date stated as 31 Oct 2028 (not stated in the June 2026 edition)
        • Rolls RoyceMerseyside, Cheshire and North Wales (SPM)Capacity changed from 17.015 MW to 7.1 MW
        • Rolls RoyceMerseyside, Cheshire and North Wales (SPM)Export capacity changed from 17.015 MW to 7.1 MW
        • Shin Etsu CHPCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
        • Shin Etsu CHPCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
        • Shin Etsu CHPCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”
        • Shin Etsu CHPCentral and Southern Scotland (SPD)Target energisation date not stated (31 Dec 2025 in the June 2026 edition)
        • Sorbie WindfarmCentral and Southern Scotland (SPD)Capacity changed from 12 MW to 7.5 MW
        • Sorbie WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 12.6 MW to 7.5 MW
        • Stanwardine Grange PV & BESSMerseyside, Cheshire and North Wales (SPM)Technology changed from Storage to Solar
        • Touch Energy ParkCentral and Southern Scotland (SPD)Capacity changed from 71.4 MW to 54 MW
        • ToyotaMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “yes” to “no”
        • ToyotaMerseyside, Cheshire and North Wales (SPM)Status changed from “accepted to connect” to “connected”
        • ToyotaMerseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
        • Williams Farm Solar (Phase 2)Merseyside, Cheshire and North Wales (SPM)Capacity changed from 16.27 MW to 10 MW
        • Williams Farm Solar (Phase 2)Merseyside, Cheshire and North Wales (SPM)Customer changed from Renewabuild to Solar Ventures
        • Williams Farm Solar (Phase 2)Merseyside, Cheshire and North Wales (SPM)Technology changed from Storage to Solar
        • Wull Muir Wind FarmCentral and Southern Scotland (SPD)Target energisation date not stated (1 Oct 2029 in the June 2026 edition)
        18 sites without a match in the other edition
        In the July 2026 edition only (3)
          In the June 2026 edition only (15)

            Grid supply points in the September 2026 edition

            Each grid supply point the edition names, the largest first, with the capacity of its sites connected and accepted to connect.

            Legacy49328 MW287 MW
            Capenhurst22217 MW384 MW
            Chapelcross12137 MW398 MW
            Carrington / Fiddlers Ferry27310 MW210 MW
            Cheshire E3–506 MW
            Connahs Quay32281 MW178 MW
            Mid Wales Hub5–430 MW
            Ince13219 MW187 MW
            Pentir1393 MW299 MW
            Frodsham16233 MW143 MW

            Sites in the September 2026 edition

            773 sites, 17.1 GW: 6.3 GW connected, 10.8 GW accepted to connect

            Site, company and substation names are shown as they appear in the registers, including capitalisation.

            Hill Farm 240MVAGreen Switch Capital LtdMerseyside, Cheshire and North Wales (SPM)SolarAccepted to connect240Cheshire E
            FWS Mill Hey FarmFirstway Solar LtdMerseyside, Cheshire and North Wales (SPM)StorageAccepted to connect199.6Cheshire E
            Manor RoadMerseyside, Cheshire and North Wales (SPM)StorageAccepted to connect179.625Capenhurst
            Aberangell FarmGGE Scotland LimitedMerseyside, Cheshire and North Wales (SPM)SolarAccepted to connect150Mid Wales
            Carnedd WenMerseyside, Cheshire and North Wales (SPM)WindAccepted to connect150Mid Wales Hub
            Clifton LaRenewables North WestMerseyside, Cheshire and North Wales (SPM)StorageAccepted to connect150Mersey A
            WinningtonEONMerseyside, Cheshire and North Wales (SPM)Gas and other fossilConnected138Carrington / Fiddlers Ferry
            Muircleugh FarmDalriada Renewables Ltd.Central and Southern Scotland (SPD)StorageAccepted to connect120Galashiels
            Pennersaughs Farm (Ecclefechan Solar & BESS)Central and Southern Scotland (SPD)StorageAccepted to connect120Chapelcross
            Benthead Farm Solar and BESSLocogen Solar Developments LtdCentral and Southern Scotland (SPD)StorageAccepted to connect113.43Kilwinning

            Tracking SPEN’s register since its March 2026 edition. Latest edition September 2026.

            QueueQuant

            Price what a delay would do to your project

            QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

            Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

            Price my project

            Get the plan that holds up best for your site, and where that answer flips.

            What you get from QueueQuant

            • The route to power that wins
            • How to size every asset on the site
            • The level of delay or curtailment at which that answer flips
            • Whether the project is worth building at all
            • How bad the worst outcomes get, at the risk level you choose

            See how we’d price it: Sell now, or wait for your Gate 2 offer?

            How power reaches a site

            A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.

            Flexible connection

            The network operator can reduce how much power the site exports or imports when the local network is busy, usually in return for connecting sooner or more cheaply.

            Yes: the register says it has one. No: the register says it doesn’t. Not stated: the register leaves it blank.