QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

High Cayton Solar

High Cayton Solar at Knaresborough

Northern Powergrid Embedded Capacity Register 1MW and Over, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
Not published by Northern Powergrid
Status
Accepted to connect
Planning consent
Granted 13 Jan 2022
North Yorkshire, reference 19/02259/FULMAJ · Source: REPD
Contract for Difference
Allocation Round 4
Customer
High Cayton Solar
Site name
High Cayton Solar
Address
High Calyon, Lands at High Cayton, Harrogate, North Yorkshire, HG3 3NB
Grid reference
Easting 428800, northing 462833
Licence area
North East (Northern Powergrid)
Grid supply point
Knaresborough
Bulk supply point
High Cayton Solar
Primary substation
High Cayton Solar Direct
Connection voltage
132 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 49 MW registered
Registered capacity
49 MW
Change to maximum export capacity
49 MW
Change to maximum import capacity
Not stated
Flexible connection
No
In a connection queue
Not published by Northern Powergrid
Date accepted
9 Nov 2017
Date connected
Not stated
Distribution reinforcement reference
Not published by Northern Powergrid
Transmission reinforcement reference
Not published by Northern Powergrid
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
13 Apr 2018
Tracked since
March 2026 edition

Change history

Tracked since the March 2026 edition, across 9 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at Knaresborough

GSP view

25 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 755 MW: 166 MW connected, 589 MW accepted to connect.

See all 25

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.

Contract for Difference

The Contracts for Difference allocation round for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition. QueueWatch matched the site to that record.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.