MINETY GSP
Grid supply point in Southern England (SEPD)
SSEN Embedded Capacity Register, November 2026 edition
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Solar | 40 | 774 MW | 360 MW | 414 MW |
| Other or not stated | 6 | 305 MW | 41 MW | 264 MW |
| Storage | 6 | 271 MW | 145 MW | 126 MW |
| Wind | 3 | 11.3 MW | 11.3 MW | – |
| Bioenergy and waste | 2 | 7.6 MW | 7.6 MW | – |
| Hydro and marine | 1 | 3.8 MW | 3.8 MW | – |
Storage capacity in MWh: not published by SSEN.
Each site is grouped by its first energy source, as the register names it.
How busy is each primary substation?
Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Primary substation | Bulk supply point | Sites | Connected | Accepted to connect | |||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| STRATTON | 2 | 4.3 MW | 68.4 MW | ||||||||||||||||||||||||||||||||||||
2 sites, 72.7 MW: 4.3 MW connected, 68.4 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||
| STRATTON | 1 | 27.2 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 27.2 MW: 27.2 MW connected
| |||||||||||||||||||||||||||||||||||||||
| STRATTON | 1 | 21.5 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 21.5 MW: 21.5 MW connected
| |||||||||||||||||||||||||||||||||||||||
| STRATTON | 1 | 19 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 19 MW: 19 MW connected
| |||||||||||||||||||||||||||||||||||||||
| STRATTON | 1 | 14.3 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 14.3 MW: 14.3 MW connected
| |||||||||||||||||||||||||||||||||||||||
| STRATTON | 1 | 8.6 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 8.6 MW: 8.6 MW connected
| |||||||||||||||||||||||||||||||||||||||
| STRATTON | 2 | 7.3 MW | – | ||||||||||||||||||||||||||||||||||||
2 sites, 7.3 MW: 7.3 MW connected
| |||||||||||||||||||||||||||||||||||||||
| STRATTON | 2 | 6.6 MW | – | ||||||||||||||||||||||||||||||||||||
2 sites, 6.6 MW: 6.6 MW connected
| |||||||||||||||||||||||||||||||||||||||
| STRATTON | 1 | 4.8 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 4.8 MW: 4.8 MW connected
| |||||||||||||||||||||||||||||||||||||||
| STRATTON | 6 | 9 MW | 227 MW | ||||||||||||||||||||||||||||||||||||
6 sites, 236 MW: 9 MW connected, 227 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||
| SWINDON | 1 | 14.3 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 14.3 MW: 14.3 MW connected
| |||||||||||||||||||||||||||||||||||||||
| SWINDON | 2 | 11.2 MW | – | ||||||||||||||||||||||||||||||||||||
2 sites, 11.2 MW: 11.2 MW connected
| |||||||||||||||||||||||||||||||||||||||
| SWINDON | 1 | 8.3 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 8.3 MW: 8.3 MW connected
| |||||||||||||||||||||||||||||||||||||||
| SWINDON | 1 | 7.6 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 7.6 MW: 7.6 MW connected
| |||||||||||||||||||||||||||||||||||||||
| SWINDON | 1 | 7.6 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 7.6 MW: 7.6 MW connected
| |||||||||||||||||||||||||||||||||||||||
| SWINDON | 1 | 6.7 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 6.7 MW: 6.7 MW connected
| |||||||||||||||||||||||||||||||||||||||
| SWINDON | 1 | 5.7 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 5.7 MW: 5.7 MW connected
| |||||||||||||||||||||||||||||||||||||||
| SWINDON | 1 | 3.8 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 3.8 MW: 3.8 MW connected
| |||||||||||||||||||||||||||||||||||||||
| SWINDON | 1 | 3.8 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 3.8 MW: 3.8 MW connected
| |||||||||||||||||||||||||||||||||||||||
| SWINDON | 1 | 2.4 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 2.4 MW: 2.4 MW connected
| |||||||||||||||||||||||||||||||||||||||
| SWINDON | 2 | – | 118 MW | ||||||||||||||||||||||||||||||||||||
2 sites, 118 MW: 118 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||
| CIRENCESTER | 2 | 14.3 MW | 12.6 MW | ||||||||||||||||||||||||||||||||||||
2 sites, 26.9 MW: 14.3 MW connected, 12.6 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||
| CIRENCESTER | 2 | – | 14 MW | ||||||||||||||||||||||||||||||||||||
2 sites, 14 MW: 14 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||
| CIRENCESTER | 1 | 9.5 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 9.5 MW: 9.5 MW connected
| |||||||||||||||||||||||||||||||||||||||
| CIRENCESTER | 1 | – | 3 MW | ||||||||||||||||||||||||||||||||||||
1 site, 3 MW: 3 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||
| CIRENCESTER | 1 | – | 2.5 MW | ||||||||||||||||||||||||||||||||||||
1 site, 2.5 MW: 2.5 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||
| CIRENCESTER | 5 | 65 MW | 55 MW | ||||||||||||||||||||||||||||||||||||
5 sites, 120 MW: 65 MW connected, 55 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||
| TOOTHILL | 2 | 1.9 MW | 70 MW | ||||||||||||||||||||||||||||||||||||
2 sites, 71.9 MW: 1.9 MW connected, 70 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||
| TOOTHILL | 1 | 46.1 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 46.1 MW: 46.1 MW connected
| |||||||||||||||||||||||||||||||||||||||
| TOOTHILL | 1 | 8.6 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 8.6 MW: 8.6 MW connected
| |||||||||||||||||||||||||||||||||||||||
| TOOTHILL | 2 | 6.4 MW | – | ||||||||||||||||||||||||||||||||||||
2 sites, 6.4 MW: 6.4 MW connected
| |||||||||||||||||||||||||||||||||||||||
| TOOTHILL | 1 | – | 5 MW | ||||||||||||||||||||||||||||||||||||
1 site, 5 MW: 5 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||
| Not stated | 1 | 95 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 95 MW: 95 MW connected
| |||||||||||||||||||||||||||||||||||||||
| Not stated | 1 | 47.4 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 47.4 MW: 47.4 MW connected
| |||||||||||||||||||||||||||||||||||||||
| Not stated | 6 | 80 MW | 230 MW | ||||||||||||||||||||||||||||||||||||
6 sites, 310 MW: 80 MW connected, 230 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||
Not found among the sites of 1 MW and over in SSEN’s November 2026 edition
3 sites last found at this grid supply point were not found among this edition’s sites of 1 MW and over by their MPAN, grid reference or name and postcode. QueueWatch keeps their pages for six months and does not say whether they have left the register.
- EWEN last found in the September 2026 edition
- PATHEON UK LTD last found in the September 2026 edition
- CIRENCESTER SOLAR PARK - PV last found in the June 2026 edition
What changed recently
Changes to sites here found in both editions of each pair, newest first.
October 2026 edition to November 2026 edition: 58 sites matched. Every October site and every November site at this grid supply point had a match in the other edition.
- CRUCIS PARK ESTATE LLPNovember 2026 editionExport capacity changed from 11 MW to 12.6 MW
- DOWN AMPNEY AIRFIELD QUARRYNovember 2026 editionExport capacity changed from 0.499 MW to 2.45 MW
- CRUCIS PARK ESTATE LLPOctober 2026 editionExport capacity changed from 12.6 MW to 11 MW
- DOWN AMPNEY AIRFIELD QUARRYOctober 2026 editionExport capacity changed from 2.45 MW to 0.499 MW
- CRUCIS PARK ESTATE LLPSeptember 2026 editionExport capacity changed from 11 MW to 12.6 MW
- DOWN AMPNEY AIRFIELD QUARRYSeptember 2026 editionExport capacity changed from 0.499 MW to 2.45 MW
- PURTON SOLAR FARMSeptember 2026 editionExport capacity changed from 0 MW to 3.2 MW
- CRUCIS PARK ESTATE LLPAugust 2026 editionExport capacity changed from 12.6 MW to 11 MW
- CRUCIS PARK ESTATE LLPJuly 2026 editionExport capacity changed from 11 MW to 12.6 MW
- CRUCIS PARK ESTATE LLPJune 2026 editionExport capacity changed from 12.6 MW to 11 MW
- DOWN AMPNEY AIRFIELD QUARRYJune 2026 editionExport capacity changed from 2.45 MW to 0.499 MW
- CRUCIS PARK ESTATE LLPMay 2026 editionExport capacity changed from 11 MW to 12.6 MW
- Site not namedApril 2026 editionExport capacity changed from 12.105 MW to 50.6 MW
- CRUCIS PARK ESTATE LLPFebruary 2026 editionExport capacity changed from 0 MW to 11 MW
- DOWN AMPNEY AIRFIELD QUARRYFebruary 2026 editionExport capacity changed from 0.9 MW to 2.45 MW
- PURTON SOLAR FARMFebruary 2026 editionExport capacity changed from 3.2 MW to 0 MW
- PARK GROUNDSJuly 2025 editionTechnology stated as Bioenergy and waste (not stated in the June 2025 edition)
- CIRENCESTER PVApril 2025 editionTechnology stated as Solar (not stated in the March 2025 edition)
- Site not namedApril 2025 editionTechnology stated as Solar (not stated in the March 2025 edition)
- CIRENCESTER SOLAR PARK - PVFebruary 2024 editionCapacity changed from 50 MW to 49 MW
- CIRENCESTER SOLAR PARK - PVFebruary 2024 editionExport capacity changed from 50 MW to 49 MW
- CIRENCESTER PVNovember 2023 editionCapacity stated as 9.5 MW (not stated in the October 2023 edition)
- CIRENCESTER PVNovember 2023 editionFlexible connection stated as “no” (not stated in the October 2023 edition)
- CIRENCESTER PVNovember 2023 editionTechnology not stated (Solar in the October 2023 edition)
- CRUCIS PARK PV FARMNovember 2023 editionCapacity stated as 14.25 MW (not stated in the October 2023 edition)
- PARK GROUNDSNovember 2023 editionCapacity changed from 6 MW to 5.7 MW
- PURLIEUS BATTERY STORAGENovember 2023 editionCapacity changed from 110.737 MW to 94.991 MW
- STANTON WATERS PVNovember 2023 editionCapacity changed from 4.211 MW to 3.8 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
How power reaches a site
A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.