REDMOSS
Grid supply point in North of Scotland (SHEPD)
SSEN Embedded Capacity Register, November 2026 edition
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Storage | 3 | 71.6 MW | – | 71.6 MW |
| Wind | 3 | 61.5 MW | 61.5 MW | – |
| Other or not stated | 2 | 37.2 MW | 15.2 MW | 22 MW |
| Bioenergy and waste | 1 | 10 MW | – | 10 MW |
| Solar | 1 | 2 MW | – | 2 MW |
Storage capacity in MWh: not published by SSEN.
Each site is grouped by its first energy source, as the register names it.
How busy is each primary substation?
Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Primary substation | Bulk supply point | Sites | Connected | Accepted to connect | |||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Not stated | 4 | 59 MW | 70 MW | ||||||||||||||||||||||||||
4 sites, 129 MW: 59 MW connected, 70 MW accepted to connect
| |||||||||||||||||||||||||||||
| Not stated | 3 | – | 33.6 MW | ||||||||||||||||||||||||||
3 sites, 33.6 MW: 33.6 MW accepted to connect
| |||||||||||||||||||||||||||||
| Not stated | 2 | 15.2 MW | 2 MW | ||||||||||||||||||||||||||
2 sites, 17.2 MW: 15.2 MW connected, 2 MW accepted to connect
| |||||||||||||||||||||||||||||
| Not stated | 1 | 2.4 MW | – | ||||||||||||||||||||||||||
1 site, 2.4 MW: 2.4 MW connected
| |||||||||||||||||||||||||||||
Not found among the sites of 1 MW and over in SSEN’s November 2026 edition
3 sites last found at this grid supply point were not found among this edition’s sites of 1 MW and over by their MPAN, grid reference or name and postcode. QueueWatch keeps their pages for six months and does not say whether they have left the register.
- BANKHEAD PV & WIND last found in the September 2026 edition
- NEWTONHILL SOLAR FARM last found in the June 2026 edition
- 49.9MW last found in the May 2026 edition
What changed recently
Changes to sites here found in both editions of each pair, newest first.
October 2026 edition to November 2026 edition: 10 sites matched. Every October site and every November site at this grid supply point had a match in the other edition.
- DRUMFORSKIE PVNovember 2026 editionExport capacity changed from 0.05 MW to 2 MW
- BANKHEAD PV & WINDSeptember 2026 editionExport capacity changed from 2.8 MW to 3.5 MW
- DRUMFORSKIE PVSeptember 2026 editionExport capacity changed from 2 MW to 0.05 MW
- BANKHEAD PV & WINDAugust 2026 editionExport capacity changed from 3.5 MW to 2.8 MW
- DRUMFORSKIE PVAugust 2026 editionExport capacity changed from 0.05 MW to 2 MW
- BANKHEAD PV & WINDJuly 2026 editionExport capacity changed from 2.8 MW to 3.5 MW
- BANKHEAD PV & WINDMay 2026 editionExport capacity changed from 3.5 MW to 2.8 MW
- BANKHEAD PV & WINDFebruary 2026 editionExport capacity changed from 2.8 MW to 3.5 MW
- CRAIGSHAW DRIVE EV & BESSDecember 2025 editionCustomer not stated (name not shown in the November 2025 edition)
- KINCARDINE OFFSHORE WINDFARMOctober 2025 editionCapacity changed from 52.211 MW to 49.6 MW
- GREENBANK CRESCENTNovember 2023 editionCapacity changed from 16 MW to 15.2 MW
- ALTENS 10MW PV + ELECTOLYSERSeptember 2023 editionCustomer stated, name not shown (not stated in the August 2023 edition)
- ALTENS 10MW PV + ELECTOLYSERSeptember 2023 editionTechnology changed from Solar to Bioenergy and waste
- CRAIGSHAW DRIVE EV & BESSSeptember 2023 editionCustomer stated, name not shown (not stated in the August 2023 edition)
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
How power reaches a site
A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.