QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Distribution / SSEN / Grid supply point

THURSO SOUTH GRID

Grid supply point in North of Scotland (SHEPD)

SSEN Embedded Capacity Register, November 2026 edition

20sites of 1 MW and over
436 MWcapacity
81 MWconnected (10 sites)
355 MWaccepted to connect (10 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage5237 MW–237 MW
Wind8160 MW42 MW118 MW
Hydro and marine220.8 MW20.8 MW–
Gas and other fossil414.6 MW14.6 MW–
Bioenergy and waste13.3 MW3.3 MW–

Storage capacity in MWh: not published by SSEN.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Not stated1559 MW355 MW
Not stated414.6 MW–
Not stated16.7 MW–

Search and filter all 20 sites at THURSO SOUTH GRID

What changed recently

Changes to sites here found in both editions of each pair, newest first.

October 2026 edition to November 2026 edition: 20 sites matched. Every October site and every November site at this grid supply point had a match in the other edition.

  • LOCHEND WINDJuly 2026 editionFlexible connection stated as “yes” (not stated in the June 2026 edition)
  • KIRKWALL PS G4April 2025 editionTechnology stated as Gas and other fossil (not stated in the March 2025 edition)
  • KIRKWALL PS G6April 2025 editionTechnology stated as Gas and other fossil (not stated in the March 2025 edition)
  • KIRKWALL PS G8April 2025 editionTechnology stated as Gas and other fossil (not stated in the March 2025 edition)
  • KIRKWALL PS G9April 2025 editionTechnology stated as Gas and other fossil (not stated in the March 2025 edition)
  • UPPER GEISLITTLE / WEYDALENovember 2023 editionCustomer changed from GVO WIND NO.40 LTD to GVO WIND NO.4DATA NOT AVAILABLE LTD
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.