BORELAND ENERGY STORAGE PARK

NEW ENGLAND LOBSTERS INTERNATIONAL LIMITED at KILLIN

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Oct 2031
Status
Accepted to connect
Planning consent
Granted 8 Sep 2025
Stirling, reference 25/00246/FUL · Source: REPD
Customer
NEW ENGLAND LOBSTERS INTERNATIONAL LIMITED
Site name
BORELAND ENERGY STORAGE PARK
Address
BORELAND ENERGY STORAGE PARK, BORELAND GLEN LOCHAY, KILLIN, STIRLING, FK21 8TT
Grid reference
Easting 255686, northing 734696
Licence area
North of Scotland (SHEPD)
Grid supply point
KILLIN
Bulk supply point
Not stated
Primary substation
KILLIN GRID
Connection voltage
33 kV
Technology group
Storage
Energy source 1
STORED ENERGY (ALL STORED ENERGY IRRESPECTVE OF THE ORIGINAL ENERGY SOURCE), STORAGE - ELECTROCHEMICAL (BATTERIES): 48 MW registered
Registered capacity
48 MW
Change to maximum export capacity
43 MW
Change to maximum import capacity
45.263 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
11 May 2023
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
August 2023 edition

What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?

Change history

Tracked since the August 2023 edition, across 40 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2025 edition
    Target energisation date stated as 31 Oct 2031 (not stated in the October 2025 edition)

Also at KILLIN

GSP view

5 other sites at this grid supply point in the November 2026 edition, 4 of them at KILLIN GRID, the same primary substation. In all, the sites here total 104 MW: 6 MW connected, 98 MW accepted to connect.

  • MORENISHOPDE UK LIMITED, Storage, KILLIN GRID primaryAccepted49.4 MW
  • ACHOMER ENERGY LTDACHOMER ENERGY LTD, Hydro and marine, KILLIN GRID primaryConnected1.9 MW
  • GLENLYONINVERVAR HYDRO DEVELOPMENT LIMITED, Hydro and marine, KILLIN GRID primaryConnected1.2 MW
  • LAIRIG A MHUIC LLPLAIRIG A MHUIC LLP, Hydro and marine, KILLIN GRID primaryConnected1.14 MW
  • GLEN DOCHARTCHAORACH HYDRO, Hydro and marine, CHAORACH primaryConnected2 MW
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.