ALLT DOMHAIN WIND FARM
At CARRADALE
SSEN Embedded Capacity Register, November 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 31 Oct 2035
- Status
- Accepted to connect
- Planning consent
- Application submitted 31 Jul 2025
Scottish Government (S36), reference ECU00003231 · Source: REPD - Customer
- Not stated
- Site name
- ALLT DOMHAIN WIND FARM
- Address
- ARNICLE FARM, GLENBARR GLENBARR, TARBERT, ARGYLL, PA29 6UZ
- Grid reference
- Easting 169349, northing 637643
- Licence area
- North of Scotland (SHEPD)
- Grid supply point
- CARRADALE
- Bulk supply point
- Not stated
- Primary substation
- CAMPBELTOWN
- Connection voltage
- 33 kV
- Technology group
- Wind
- Energy source 1
- WIND, ONSHORE WIND TURBINES: 64.8 MW registered
- Registered capacity
- 64.8 MW
- Change to maximum export capacity
- 0.1 MW
- Change to maximum import capacity
- 0.1 MW
- Flexible connection
- Not stated
- In a connection queue
- Not published by SSEN
- Date accepted
- 25 Jun 2025
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SSEN
- Transmission reinforcement reference
- Not published by SSEN
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 10 Feb 2026
- Tracked since
- July 2025 edition
Change history
Tracked since the July 2025 edition, across 17 editions.
Changes to the details QueueWatch tracks, newest first.
- November 2026 editionExport capacity changed from 64.8 MW to 0.1 MW
- September 2026 editionExport capacity changed from 0.1 MW to 64.8 MW
- July 2026 editionExport capacity changed from 64.8 MW to 0.1 MW
- November 2025 editionTarget energisation date stated as 31 Oct 2035 (not stated in the October 2025 edition)
Also at CARRADALE
GSP view21 other sites at this grid supply point in the November 2026 edition, 2 of them at CAMPBELTOWN, the same primary substation. In all, the sites here total 694 MW: 188 MW connected, 506 MW accepted to connect.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
Planning consent
The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.
How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.