DENHEAD SOLAR MACDUFF GSP

MUIRDEN ENERGY LLP at MACDUFF

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Mar 2029
Status
Accepted to connect
Planning consent
Granted 18 Apr 2024
Aberdeenshire, reference APP/2023/2040 · Source: REPD
Customer
MUIRDEN ENERGY LLP
Site name
DENHEAD SOLAR MACDUFF GSP
Address
CULBEUCHLY, BANFF, ABERDEENSHIRE, AB45 3AJ
Grid reference
Easting 364887, northing 862399
Licence area
North of Scotland (SHEPD)
Grid supply point
MACDUFF
Bulk supply point
Not stated
Primary substation
MACDUFF GRID
Connection voltage
33 kV
Technology group
Solar
Energy source 1
SOLAR, PHOTOVOLTAIC: 20 MW registered
Registered capacity
20 MW
Change to maximum export capacity
0.1 MW
Change to maximum import capacity
0.1 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
27 May 2025
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
August 2023 edition

Change history

Tracked since the August 2023 edition, across 40 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2026 edition
    Export capacity changed from 20 MW to 0.1 MW
  • September 2026 edition
    Export capacity changed from 0.1 MW to 20 MW
  • July 2026 edition
    Export capacity changed from 20 MW to 0.1 MW
  • May 2026 edition
    Export capacity changed from 0.1 MW to 20 MW
  • April 2026 edition
    Export capacity changed from 20 MW to 0.1 MW
  • November 2025 edition
    Target energisation date stated as 31 Mar 2029 (not stated in the October 2025 edition)
  • June 2025 edition
    Technology changed from Bioenergy and waste to Solar
  • June 2025 edition
    Flexible connection not stated (“no” in the May 2025 edition)

Also at MACDUFF

GSP view

20 other sites at this grid supply point in the November 2026 edition, 16 of them at MACDUFF GRID, the same primary substation. In all, the sites here total 398 MW: 79 MW connected, 319 MW accepted to connect.

See all 20

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.