Flatterton Farm
Big Battery (Flatterton Farm) Ltd at Spango Valley
SPEN Embedded Capacity Register >1MW, September 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 28 Jun 2028
- Status
- Accepted to connect
- Planning consent
- Granted 5 Jun 2024
Inverclyde, reference 23/0205/IC · Source: REPD - Customer
- Big Battery (Flatterton Farm) Ltd
- Site name
- Flatterton Farm
- Address
- Flatterton Farm, Greenock, Inverclyde, PA16 0AD
- Grid reference
- Easting 222679, northing 674478
- Licence area
- Central and Southern Scotland (SPD)
- Grid supply point
- Spango Valley
- Bulk supply point
- Not stated
- Primary substation
- Not stated
- Connection voltage
- 33 kV
- Technology group
- Storage
- Energy source 1
- Stored Energy, Storage - Electrochemical (Batteries): 58.8 MW registered
- Registered capacity
- 58.8 MW
- Change to maximum export capacity
- 50 MW
- Change to maximum import capacity
- 50 MW
- Flexible connection
- Yes
- In a connection queue
- Yes
- Date accepted
- 30 Sep 2022
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SPEN
- Transmission reinforcement reference
- SPT-RI-003, SPT-RI-1551, SPT-RI-1873, SPT-RI-1968, SPT-RI-200, SPT-RI-2073, SPT-RI-2083, SPT-RI-2084, SPT-RI-2085, SPT-RI-2268, SPT-RI-231, SPT-RI-2311, SPT-RI-243, SPT-RI-2862, SPT-RI-2876, SPT-RI-2877, SPT-RI-2943, SPT-RI-3002, SPT-RI-3159, SPT-RI-3263, SPT-RI-3285, SPT-RI-3309, SPT-RI-3315, SPT-RI-3498, SPT-RI-3513, SPT-RI-3884, SPT-RI-4209, SPT-RI-4210
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 25 Nov 2022
- Tracked since
- March 2026 edition
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Change history
Tracked since the March 2026 edition, across 7 editions.
Changes to the details QueueWatch tracks, newest first.
- June 2026 editionCapacity changed from 53.2 MW to 58.8 MW
- June 2026 editionTarget energisation date moved from 30 Jun 2027 to 28 Jun 2028 (12 months later)
Also at Spango Valley
GSP view2 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 99.8 MW: 99.8 MW accepted to connect.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
Planning consent
The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.
How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.