Distribution / UKPN / Grid supply point

Kemsley

Grid supply point in South Eastern Power Networks (SPN)

UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition

28sites of 1 MW and over
534 MWcapacity
284 MWconnected (19 sites)
250 MWaccepted to connect (9 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage3199 MW49 MW150 MW
Solar15136 MW49 MW87 MW
Bioenergy and waste290 MW90 MW–
Gas and other fossil585 MW71 MW14 MW
Wind324.6 MW24.6 MW–

Storage capacity in MWh: no site here states any.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Sittingbourne Grid 33kV112 MW–
Sittingbourne Grid 33kV15 MW–
Sittingbourne Grid 33kV11.7 MW–
Sittingbourne Grid 33kV640.4 MW–
Grovehurst Energy 33kV12 MW–
Grovehurst Energy 33kV242 MW14 MW
Sheerness Grid 33kV14.6 MW–
Sheerness Grid 33kV11 MW–
Sheerness Grid 33kV336 MW–
Sittingbourne Grid1–40.8 MW
Sittingbourne2–35 MW
Grovehurst Grid1–4.9 MW
Grovehurst1–3.1 MW
Not stated125 MW–
Not stated5114 MW153 MW

Search and filter all 28 sites at Kemsley

What changed recently

Changes to sites here found in both editions of each pair, newest first.

October 2026 edition to November 2026 edition: 28 sites matched. Every October site and every November site at this grid supply point had a match in the other edition.

  • School LaneNovember 2026 editionTarget energisation date moved from 30 Jan 2025 to 10 Jan 2026 (11 months later)
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.