Distribution / UKPN / Grid supply point

Kingsnorth

Grid supply point in South Eastern Power Networks (SPN)

UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition

18sites of 1 MW and over
241 MWcapacity
125 MWconnected (14 sites)
116 MWaccepted to connect (4 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Gas and other fossil898.7 MW96.7 MW2 MW
Storage254.6 MW5.1 MW49.5 MW
Bioenergy and waste453.6 MW3.7 MW49.9 MW
Solar434 MW19 MW15 MW

Storage capacity in MWh: no site here states any.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Medway Grid19.5 MW–
Medway Grid16.5 MW–
Medway Grid15.1 MW–
Chatham Grid1–15 MW
Medway Grid 33kV26.2 MW–
Medway Grid 33kV25.7 MW–
Medway Grid 33kV11.7 MW–
Not stated1–49.9 MW
Not stated424.8 MW2 MW
Not stated225 MW–
Not stated240 MW49.5 MW

Search and filter all 18 sites at Kingsnorth

What changed recently

Changes to sites here found in both editions of each pair, newest first.

October 2026 edition to November 2026 edition: 18 sites matched. Every October site and every November site at this grid supply point had a match in the other edition.

  • Kingsnorth Power StationNovember 2026 editionTarget energisation date moved from 31 Dec 2024 to 31 Oct 2026 (22 months later)
  • Land At Harp FarmNovember 2026 editionTarget energisation date moved from 30 Apr 2025 to 31 Oct 2027 (30 months later)
  • Land To The North Of Sewage WorksNovember 2026 editionTarget energisation date moved from 31 Dec 2024 to 31 Oct 2026 (22 months later)
  • Offham QuarryNovember 2026 editionExport capacity stated as 9.5 MW (not stated in the October 2026 edition)
  • Offham QuarryNovember 2026 editionTarget energisation date not stated (30 Apr 2025 in the October 2026 edition)
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.