Norwich
Grid supply point in Eastern Power Networks (EPN)
UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Solar | 40 | 708 MW | 230 MW | 478 MW |
| Storage | 6 | 648 MW | – | 648 MW |
| Gas and other fossil | 12 | 461 MW | 461 MW | – |
| Wind | 6 | 411 MW | 411 MW | – |
| Bioenergy and waste | 11 | 17.9 MW | 17.9 MW | – |
Storage capacity in MWh: no site here states any.
Each site is grouped by its first energy source, as the register names it.
How busy is each primary substation?
Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Primary substation | Bulk supply point | Sites | Connected | Accepted to connect | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Sall Grid 33kV | 1 | 9 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 9 MW: 9 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Sall Grid 33kV | 1 | 3 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 3 MW: 3 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Sall Grid 33kV | 2 | 2.7 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 2.7 MW: 2.7 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Sall Grid 33kV | 1 | 1.5 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 1.5 MW: 1.5 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Sall Grid 33kV | 1 | 1.1 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 1.1 MW: 1.1 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Sall Grid 33kV | 9 | 59 MW | 45 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
9 sites, 104 MW: 59 MW connected, 45 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Trowse Grid 33kV | 1 | 3.8 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 3.8 MW: 3.8 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Trowse Grid 33kV | 1 | 1.6 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 1.6 MW: 1.6 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Trowse Grid 33kV | 1 | 1 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 1 MW: 1 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Trowse Grid 33kV | 8 | 33 MW | 71 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
8 sites, 104 MW: 33 MW connected, 71 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| GT Yarmouth Grid 33kV | 2 | 4.6 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 4.6 MW: 4.6 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| GT Yarmouth Grid 33kV | 2 | 90.8 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 90.8 MW: 90.8 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Thorpe Grid 33kV | 3 | 44.6 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3 sites, 44.6 MW: 44.6 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Thorpe Grid 33kV | 2 | 9 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 9 MW: 9 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Thorpe Grid 33kV | 1 | 6 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 6 MW: 6 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Thorpe Grid 33kV | 1 | 5 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 5 MW: 5 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Thorpe Grid 33kV | 3 | 4.1 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3 sites, 4.1 MW: 4.1 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Thorpe Grid 33kV | 3 | 15.8 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3 sites, 15.8 MW: 15.8 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Sall Grid 132/33kV | 1 | – | 20 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 20 MW: 20 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Sall Grid 132/33kV | 1 | – | 15 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 15 MW: 15 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Sall Grid 132/33kV | 1 | – | 30 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 30 MW: 30 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Earlham Grid 33kV | 2 | 6.2 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 6.2 MW: 6.2 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Earlham Grid 33kV | 2 | 2.5 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 2.5 MW: 2.5 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Earlham Grid 33kV | 1 | 2.2 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 2.2 MW: 2.2 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Earlham Grid 33kV | 3 | 46.8 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3 sites, 46.8 MW: 46.8 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Earlham 132kV | 1 | – | 50 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 50 MW: 50 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Sall Grid 132kV | 1 | – | 50 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 50 MW: 50 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Gorleston Grid 33kV | 2 | 8.3 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 8.3 MW: 8.3 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Gorleston Grid 33kV | 1 | – | 30 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 30 MW: 30 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Lowestoft Grid 33kV | 2 | 13.3 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 13.3 MW: 13.3 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Not stated | 2 | 3.3 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 3.3 MW: 3.3 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Not stated | 12 | 0.8 GW | 0.8 GW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12 sites, 1.6 GW: 0.8 GW connected, 0.8 GW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Not found among the sites of 1 MW and over in UKPN’s November 2026 edition
1 site last found at this grid supply point was not found among this edition’s sites of 1 MW and over by its MPAN, grid reference or name and postcode. QueueWatch keeps its page for six months and does not say whether it has left the register.
- Whitlingham STW Norfolk last found in the September 2026 edition
What changed recently
Changes to sites here found in both editions of each pair, newest first.
October 2026 edition to November 2026 edition: 75 sites matched. Every October site and every November site at this grid supply point had a match in the other edition.
- (ANM) Beerhouse FarmNovember 2026 editionTarget energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
- (ANM) Bracon AshNovember 2026 editionTarget energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
- (ANM) Bunwell RoadNovember 2026 editionTarget energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
- (ANM) Land East Of Drayton LaneNovember 2026 editionTarget energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
- (ANM) Land South Of A47November 2026 editionTarget energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
- Dereham RoadNovember 2026 editionTarget energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
- PV Solar (Carlton Farm)October 2026 editionCapacity changed from 5.5 MW to 5 MW
- PV Solar (Carlton Farm)October 2026 editionExport capacity changed from 5.5 MW to 5 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
How power reaches a site
A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.