Pelham
Grid supply point in Eastern Power Networks (EPN)
UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Solar | 29 | 666 MW | 134 MW | 532 MW |
| Storage | 4 | 130 MW | 70 MW | 60 MW |
| Gas and other fossil | 4 | 31.5 MW | 24 MW | 7.5 MW |
| Bioenergy and waste | 4 | 6.5 MW | 6.5 MW | – |
| Wind | 1 | 4.9 MW | – | 4.9 MW |
Storage capacity in MWh: no site here states any.
Each site is grouped by its first energy source, as the register names it.
How busy is each primary substation?
Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Primary substation | Bulk supply point | Sites | Connected | Accepted to connect | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Thaxted Grid 33kV | 1 | – | 7.5 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 7.5 MW: 7.5 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Thaxted Grid 33kV | 1 | 6 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 6 MW: 6 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Thaxted Grid 33kV | 1 | 1.2 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 1.2 MW: 1.2 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Thaxted Grid 33kV | 10 | 95 MW | 44 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10 sites, 139 MW: 95 MW connected, 44 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Belchamp Grid 33kV | 1 | 4 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 4 MW: 4 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Belchamp Grid 33kV | 8 | 73 MW | 74 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
8 sites, 147 MW: 73 MW connected, 74 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Bishops Stortford Grid 33kV | 3 | 3.5 MW | 6 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3 sites, 9.5 MW: 3.5 MW connected, 6 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Bishops Stortford Grid 33kV | 1 | – | 3.6 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 3.6 MW: 3.6 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Bishops Stortford Grid 33kV | 1 | 1.8 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 1.8 MW: 1.8 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Bishops Stortford Grid 33kV | 3 | – | 60 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3 sites, 60 MW: 60 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Thaxted Grid | 1 | – | 4.9 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 4.9 MW: 4.9 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Thaxted Grid | 1 | – | 60 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 60 MW: 60 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Thaxted Grid 132/33kV | 1 | – | 30 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 30 MW: 30 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Melbourn Grid 33kV | 1 | – | 4.9 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 4.9 MW: 4.9 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Melbourn Grid 33kV | 1 | – | 3 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 3 MW: 3 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Not stated | 7 | 50 MW | 307 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
7 sites, 357 MW: 50 MW connected, 307 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Not found among the sites of 1 MW and over in UKPN’s November 2026 edition
1 site last found at this grid supply point was not found among this edition’s sites of 1 MW and over by its MPAN, grid reference or name and postcode. QueueWatch keeps its page for six months and does not say whether it has left the register.
- (ANM) Hill Green Farm last found in the October 2026 edition
What changed recently
Changes to sites here found in both editions of each pair, newest first.
October 2026 edition to November 2026 edition: 39 sites matched. 4 sites at this grid supply point couldn’t be matched between the two editions, because their details changed or they appear in only one.
4 sites without a match in the other edition
In the November 2026 edition only (3)
- Backlane Solar FarmEastern Power Networks (EPN)Accepted to connect4.9 MW
- Meldreth RoadEastern Power Networks (EPN)Accepted to connect3 MW
- Twinstead Solar FarmEastern Power Networks (EPN)Accepted to connect60 MW
In the October 2026 edition only (1)
- (ANM) Hill Green FarmEastern Power Networks (EPN)Accepted to connect95 MW
- (ANM) Land At Warmans FarmNovember 2026 editionTarget energisation date moved from 31 Dec 2028 to 31 Oct 2029 (10 months later)
- (ANM) Rowley Hill RoadNovember 2026 editionTarget energisation date moved from 12 Jan 2024 to 31 Oct 2026 (34 months later)
- (ANM) Water Hall FarmNovember 2026 editionTarget energisation date moved from 31 Dec 2028 to 31 Oct 2029 (10 months later)
- Berden Hall Farm PVNovember 2026 editionTarget energisation date moved from 20 Jun 2025 to 31 Mar 2027 (21 months later)
- Knowl Green FarmNovember 2026 editionTarget energisation date moved from 31 Dec 2024 to 31 Jul 2026 (19 months later)
- Land Near Hadham RdNovember 2026 editionTarget energisation date moved from 31 Dec 2028 to 31 Oct 2029 (10 months later)
- Maggotts EndNovember 2026 editionTarget energisation date moved from 12 Jan 2024 to 31 Oct 2029 (70 months later)
- West Thaxted Solar FarmNovember 2026 editionTarget energisation date moved from 12 Jan 2024 to 1 Dec 2025 (23 months later)
- Wickham HallNovember 2026 editionTarget energisation date moved from 12 Jan 2024 to 1 Dec 2025 (23 months later)
- Wickham HallNovember 2026 editionTarget energisation date moved from 6 Jun 2025 to 6 Jun 2026 (12 months later)
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
How power reaches a site
A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.