Red Tile Windfarm - 2

Fenland Windfarms Limited at Eaton Socon

UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Date connected
8 Dec 2006
Status
Connected
Planning consent
Granted 7 Feb 2005
Huntingdonshire, reference 0302827FUL · Source: REPD
Customer
Fenland Windfarms Limited
Site name
Red Tile Windfarm - 2
Address
Straight Drove, Huntingdon, Cambridgeshire, PE28 2UH
Grid reference
Easting 534850, northing 283160
Licence area
Eastern Power Networks (EPN)
Grid supply point
Eaton Socon
Bulk supply point
Huntingdon Grid 33kV
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Wind
Energy source 1
Wind, Onshore wind turbines: 14 MW registered
Registered capacity
14 MW
Maximum export capacity
14 MW
Maximum import capacity
Not stated
Flexible connection
No
In a connection queue
No
Date accepted
Not stated
Target energisation date
Not stated
Distribution reinforcement reference
Not published by UKPN
Transmission reinforcement reference
Not stated
Export MPAN
1030037258625
Import MPAN
Not stated
Last updated
13 Nov 2020
Tracked since
September 2026 edition

Change history

Tracked since the September 2026 edition, across 3 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at Eaton Socon

GSP view

40 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 950 MW: 276 MW connected, 674 MW accepted to connect.

See all 40

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.