Bhlaraidh Wind Farm
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Onshore wind
- Total capacity
- 108 MW
- Connected now
- 108 MW
- Still to connect
- 0 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000034
- In the register since
- January 2021 or earlier