Coire Glas Pumped Storage
- Connection date
- 31 Oct 2029
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Pumped storage
- Total capacity
- 1,296 MW
- Connected now
- 0 MW
- Still to connect
- 1,296 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000073
- In the register since
- January 2021 or earlier
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 612 | 612 | 31 Oct 2029 | Not stated | Consents Approved |
| 2 | 0 | 684 | 1,296 | 31 Oct 2029 | Not stated | Scoping |
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 26 Apr 2024 registerStage 1: Connection date moved from 1 Dec 2027 to 31 Oct 2029 (+23 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Coire Glas to Coire Glas GSP)
Also at Coire Glas GSP
Substation viewNo other projects in the register at this connection point.