Kilbraur Wind Farm
KILBRAUR WIND ENERGY LIMITED at Kilbraur Wind Farm Substation
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Onshore wind
- Total capacity
- 67 MW
- Connected now
- 67 MW
- Still to connect
- 0 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000226
- In the register since
- January 2021 or earlier
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 23 Dec 2022 registerSubstation name updated in the register (from Kilbraur Wind Farm to Kilbraur Wind Farm Substation)
Also at Kilbraur Wind Farm Substation
Substation view1 other project, 79.2 MW still to connect at this substation in total.