Dogger Bank Project C
DOGGERBANK OFFSHORE WIND FARM PROJECT 3 PROJCO LIMITED at Lackenby 400kV Substation
- Connection date
- 1 Apr 2025
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Offshore wind
- Total capacity
- 1,200 MW
- Connected now
- 0 MW
- Still to connect
- 1,200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000409
- In the register since
- January 2021 or earlier
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 19 Dec 2025 registerConnection point changed from Teeside Connection Node A 132kV Substation to Lackenby 400kV Substation
- 30 Sep 2025 registerConnection point changed from Lackenby GSP to Teeside Connection Node A 132kV Substation
- 23 Dec 2022 registerSubstation name updated in the register (from Lackenby to Lackenby GSP)
- 29 Jul 2022 registerCustomer changed from DOGGERBANK OFFSHORE WIND FARM PROJECT 3 HOLDCO LIMITED to DOGGERBANK OFFSHORE WIND FARM PROJECT 3 PROJCO LIMITED
- 29 Apr 2022 registerCapacity changed from 1,320 MW to 1,200 MW
- 30 Mar 2022 registerConnection date moved from 1 Apr 2024 to 1 Apr 2025 (+12 months)
- 28 Jan 2022 registerRenamed from Dogger Bank Project 2
- 30 Nov 2021 registerCapacity changed from 1,500 MW to 1,320 MW
- 28 May 2021 registerConnection point changed from Dogger Bank 220kV Offshores to Lackenby
Also at Lackenby 400kV Substation
Substation view2 other projects, 1.8 GW still to connect at this substation in total.