Enderby Tertiary
- Connection date
- 31 Aug 2028 +13 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Solar
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000430
- In the register since
- January 2021 or earlier
Read our analysis: Gate 2 in the transmission queue
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 16 Oct 2026 registerGiven a Gate 2 connection offer
- 13 Oct 2026 registerConnection date moved from 1 Aug 2027 to 31 Aug 2028 (+13 months)
- 5 Oct 2026 registerStatus changed from Scoping to Consents Approved
- 24 Dec 2024 registerConnection date moved from 1 May 2024 to 1 Aug 2027 (+39 months)
- 31 May 2024 registerTechnology changed from Thermal to Solar
- 30 Jun 2023 registerSubstation name updated in the register (from Enderby 400kV to Enderby 400kV Substation)
- 29 Jun 2021 registerCustomer changed from ENDERBY SOLAR LIMITED to CLUMP FARM SOLAR LIMITED
Also at Enderby 400kV Substation
Substation view3 other projects, 2.1 GW still to connect at this substation in total.