- Connection date
- 26 Jul 2028
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 17 Feb 2023
Welsh Government (NSIP), reference DNS/3251528 · Source: REPD - Contract for Difference
- Allocation Round 7
- Technology
- Offshore wind
- Total capacity
- 95.3 MW
- Connected now
- 0 MW
- Still to connect
- 95.3 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000471
- In the register since
- January 2021 or earlier
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 28 Jun 2024 registerCapacity changed from 91 MW to 95.3 MW
- 28 Jun 2024 registerConnection date moved from 2 Nov 2026 to 26 Jul 2028 (+21 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Pembroke 132kV to Pembroke 132kV Substation)
Also at Pembroke 132kV Substation
Substation view1 other project, 215 MW still to connect at this substation in total.