Walpole 1 (Tertiary)
- Connection date
- 1 Aug 2025
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000556
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 27 Jun 2025 registerConnection date moved from 15 Jul 2025 to 1 Aug 2025 (+1 month)
- 28 Feb 2025 registerStage removed (7.1 MW from 31 Oct 2023)
- 31 Jan 2025 registerStage 1: Capacity changed from 49.9 MW to 57 MW
- 31 Jan 2025 registerStage 1: Connection date moved from 1 May 2023 to 15 Jul 2025 (+26 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Walpole 400kV to Walpole 400kV Substation)
Also at Walpole 400kV Substation
Substation view4 other projects, 2.9 GW still to connect at this substation in total.
- Walpole Grid Services FacilityConrad (Walpole) Limited, Other, Not statedJul 20260 MW
- Norfolk001EPL NEWCO1 LIMITED, Storage with solar or wind, Not statedNov 2031860 MW
- Walpole Flexible GenerationFLEXIBLE GENERATION 1 LTD, Thermal (gas, biomass, waste), Not statedJun 20332 GW
- Sutton BridgeSUTTON BRIDGE POWER GENERATION, Thermal (gas, biomass, waste), Not statedConnected850 MW