Armadale Wind Farm
WIND DEVELOPMENT HOLDINGS LIMITED at Armadale 400kv Substation
- Connection date
- Left 30 Sep 2025
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Storage + Onshore wind
- Total capacity
- 99 MW
- Connected now
- 0 MW
- Still to connect
- 99 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000557
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 30 Sep 2025 registerLeft the register (99 MW from 1 Aug 2027)
- 31 May 2024 registerConnection point changed from Armadale 132/33kV Substation to Armadale 400kv Substation
- 26 Mar 2024 registerTechnology changed from Onshore wind to Storage, Onshore wind
- 30 May 2023 registerConnection date moved from 1 Jun 2026 to 1 Aug 2027 (+14 months)
- 23 Dec 2022 registerConnection point changed from Armadale Windfarm 132/33kV Substation to Armadale 132/33kV Substation
- 25 Feb 2022 registerConnection date moved from 31 Aug 2025 to 1 Jun 2026 (+9 months)
- 29 Jun 2021 registerCustomer changed from BROOKFIELD RENEWABLE UK LIMITED to WIND DEVELOPMENT HOLDINGS LIMITED
Also at Armadale 400kv Substation
Substation viewNo other projects in the register at this connection point.