Sellindge (Tertiary)
- Connection date
- 31 Oct 2028
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Storage
- Total capacity
- 76 MW
- Connected now
- 0 MW
- Still to connect
- 76 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001067
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 49.9 | 49.9 | 31 Oct 2028 | Not stated | Awaiting Consents |
| 2 | 0 | 26.1 | 76.0 | 31 Oct 2031 | Not stated | Awaiting Consents |
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 29 Jul 2025 registerRestructured from 1 stage (49.9 MW from 1 Nov 2024) to 2 stages (49.9 MW from 31 Oct 2028, 26.1 MW from 31 Oct 2031). First connection date +48 months
- 23 Dec 2022 registerSubstation name updated in the register (from Sellindge 400kV to Sellindge 400kV Substation)
Also at Sellindge 400kV Substation
Substation view2 other projects, 576 MW still to connect at this substation in total.