Burwell (Tertiary)
- Connection date
- 30 Jun 2029
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001109
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 30 Jun 2023 registerCapacity changed from 49.9 MW to 57 MW
- 30 Jun 2023 registerConnection date moved from 1 Nov 2022 to 30 Jun 2029 (+80 months)
- 23 Dec 2022 registerConnection point changed from Burwell 400kV to Burwell Main 400kV Substation
Also at Burwell Main 400kV Substation
Substation view1 other project, 57 MW still to connect at this substation in total.