Tillbridge Solar
- Connection date
- 27 Aug 2028
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 14 Oct 2025
Tillbridge Solar Project (EN010142) · Source: Planning Inspectorate - Technology
- Storage + Solar
- Total capacity
- 500 MW
- Connected now
- 0 MW
- Still to connect
- 500 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001126
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 24 Dec 2024 registerConnection date moved from 1 Aug 2028 to 27 Aug 2028 (+1 month)
- 31 May 2024 registerConnection date moved from 1 Oct 2027 to 1 Aug 2028 (+10 months)
- 28 Apr 2023 registerRenamed from Greta II
- 30 Jun 2022 registerCustomer changed from GRETA II LIMITED to TILLBRIDGE SOLAR LIMITED
- 30 Mar 2022 registerSubstation name updated in the register (from Cottam 400kV to Cottam 400kV Substation)
- 28 Sep 2021 registerCustomer changed from GRETA I LIMITED to GRETA II LIMITED
- 31 Aug 2021 registerConnection point changed from High Marnham Substation 275kV to Cottam 400kV
Also at Cottam 400kV Substation
Substation view4 other projects, 2.1 GW still to connect at this substation in total.
- Cottam Solar PV + BESSCOTTAM SOLAR PROJECT LIMITED, Storage with solar or wind, Gate 2Sep 2029600 MW
- CottamGATE BURTON ENERGY PARK LIMITED, Storage with solar or wind, Not statedOct 2029500 MW
- Cottam PV & BESSO&G Solar (SPV 44) Limited, Storage with solar or wind, Not statedOct 2033500 MW
- CDCLUniper UK Limited, Thermal (gas, biomass, waste), Not statedConnected445 MW