Derwent Solar PV Array
- Connection date
- 31 May 2032
- Gate
- Not stated
- Status
- Scoping
- Technology
- Solar
- Total capacity
- 160 MW
- Connected now
- 0 MW
- Still to connect
- 160 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001648
- In the register since
- March 2022
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 30 Mar 2022 registerAdded to the register
Also at Thornton 400kV Substation
Substation view3 other projects, 1.8 GW still to connect at this substation in total. 800 MW is due to connect here before this project’s connection date of 31 May 2032.