Hinkley Point C
NNB GENERATION COMPANY (HPC) LIMITED at Shurton 400kV Substation
- Connection date
- 31 Mar 2029
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 19 Mar 2013
Hinkley Point C New Nuclear Power Station (EN010001) · Source: Planning Inspectorate - Technology
- Nuclear
- Total capacity
- 3,340 MW
- Connected now
- 0 MW
- Still to connect
- 3,340 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001674
- In the register since
- January 2021 or earlier
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 1,670 | 1,670 | 31 Mar 2029 | Not stated | Scoping |
| 2 | 0 | 1,670 | 3,340 | 31 Jul 2030 | Not stated | Scoping |
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 27 Jan 2026 registerConnection point changed from Hinkley Point 400kV Substation to Shurton 400kV Substation
- 28 Feb 2025 registerConnection point changed from Shurton 400kV GIS Substation to Hinkley Point 400kV Substation
- 28 Feb 2025 registerStage 1: Connection date moved from 6 Apr 2027 to 31 Mar 2029 (+24 months)
- 28 Feb 2025 registerStage 2: Connection date moved from 6 Apr 2028 to 31 Jul 2030 (+28 months)
- 31 Jan 2025 registerStage 1: Status changed from Under Construction/Commissioning to Scoping
- 31 Jan 2025 registerStage 2: Status changed from Under Construction/Commissioning to Scoping
- 30 Jul 2024 registerCustomer changed from EDF ENERGY NUCLEAR GENERATION LIMITED to NNB GENERATION COMPANY (HPC) LIMITED
- 30 Jul 2024 registerConnection point changed from Hinkley Point 400kV Substation to Shurton 400kV GIS Substation
- 30 Jul 2024 registerStage 1: Connection date moved from 9 Feb 2026 to 6 Apr 2027 (+14 months)
- 30 Jul 2024 registerStage 2: Connection date moved from 14 Mar 2027 to 6 Apr 2028 (+13 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Hinkley Point 400kV to Hinkley Point 400kV Substation)
- 28 Jan 2022 registerStage 1: Connection date moved from 6 Dec 2024 to 9 Feb 2026 (+14 months)
- 28 Jan 2022 registerStage 1: Status changed from Consents Approved to Under Construction/Commissioning
- 28 Jan 2022 registerStage 2: Connection date moved from 6 Dec 2025 to 14 Mar 2027 (+15 months)
- 28 Jan 2022 registerStage 2: Status changed from Consents Approved to Under Construction/Commissioning
Also at Shurton 400kV Substation
Substation viewNo other projects in the register at this connection point.