Kearsley North Green Energy Centre
Kearsley North Green NG Limited at Kearsley 275kV Substation
- Connection date
- 31 Oct 2028
- Gate
- Not stated
- Status
- Scoping
- Technology
- Demand + Storage + Solar
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001793
- In the register since
- March 2022
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 30 Sep 2025 registerStage removed (0 MW from 1 Nov 2033)
- 29 Jul 2025 registerCustomer changed from INNOVA RENEWABLES LIMITED to Kearsley North Green NG Limited
- 27 Jun 2025 registerRestructured from 1 stage (400 MW from 31 Oct 2028) to 2 stages (400 MW from 31 Oct 2028, 0 MW from 1 Nov 2033)
- 23 Dec 2022 registerSubstation name updated in the register (from Kearsley to Kearsley GSP)
- 30 Mar 2022 registerAdded to the register
Also at Kearsley 275kV Substation
Substation view1 other project, 450 MW still to connect at this substation in total.