Callisterhall Wind Farm
- Connection date
- 27 Apr 2029
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 45.5 MW
- Connected now
- 0 MW
- Still to connect
- 45.5 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001965
- In the register since
- August 2022
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 20 Oct 2026 registerMarked as Gate 1
- 30 Aug 2022 registerAdded to the register
Also at Callisterhall 132kV
Substation viewNo other projects in the register at this connection point.