Pembroke BESS and Solar Station
Renesola Hercules Energy 1 Limited at Pembroke 400kV Substation
- Connection date
- 31 Oct 2028
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Storage + Solar
- Total capacity
- 99.9 MW
- Connected now
- 0 MW
- Still to connect
- 99.9 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002003
- In the register since
- November 2022
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 30 Jun 2023 registerConnection point changed from Alverdiscott 400kV Substation to Pembroke 400kV Substation
- 30 May 2023 registerConnection point changed from Pembroke 400kV Substation to Alverdiscott 400kV Substation
- 28 Apr 2023 registerSubstation name updated in the register (from Pembroke 400kV to Pembroke 400kV Substation)
- 29 Nov 2022 registerAdded to the register
Also at Pembroke 400kV Substation
Substation view5 other projects, 1.2 GW still to connect at this substation in total.
- Llŷr Floating WindLlŷr Floating Wind Limited, Offshore wind, Not statedOct 2028200 MW
- Pembroke BESSRWE Generation UK Plc, Storage, Gate 2Mar 2029350 MW
- Llywelyn Floating Offshore Wind FarmRenantis UK Limited, Offshore wind, Gate 1Mar 2029300 MW
- Valorous Offshore Wind FarmBlue Gem Wind Limited, Offshore wind, Not statedOct 2031300 MW
- Pembroke Power StationRWE Generation UK Plc, Other, Not statedConnected2.2 GW