Celtic 2 Offshore Wind Farm
- Connection date
- 31 Oct 2031
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Offshore wind
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002007
- In the register since
- October 2022
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 10 Oct 2026 registerListed again
- 18 Sep 2026 registerNot in this register
- 1 Sep 2026 registerCustomer changed from RWE Renewables UK Limited to RWE Offshore Wind
- 1 May 2026 registerMarked as Gate 1
- 31 Jan 2023 registerConnection point changed from Pembroke 400kV to Alverdiscott 400kV Substation
- 23 Dec 2022 registerConnection point changed from Alverdiscott 400kV Substation to Pembroke 400kV
- 28 Oct 2022 registerAdded to the register
Also at Alverdiscott 400kV Substation
Substation view12 other projects, 10.3 GW still to connect at this substation in total. 350 MW is due to connect here before this project’s connection date of 31 Oct 2031.
- Petroc Offshore Wind FarmBLUEFLOAT ENERGY UK HOLDINGS LIMITED, Offshore wind, Gate 1Mar 2029300 MW
- AlverdiscottPIVOTED POWER LLP, Storage, Gate 1Aug 2031100 MW
- Gwynt Glas Offshore Wind FarmGWYNT GLAS OFFSHORE WIND FARM LIMITED, Offshore wind, Gate 1Oct 2031300 MW
- Merlin 2 Offshore WindfarmOFFSHORE WIND LIMITED, Offshore wind, Gate 1Oct 20311.5 GW
- Merlin Offshore Wind FarmOFFSHORE WIND LIMITED, Offshore wind, Gate 1Oct 2031300 MW
- Morwind 300Morwind Ltd, Offshore wind, Gate 1Oct 2031300 MW
- Cormoran Offshore Wind FarmSouth West Wind Holdco Limited, Offshore wind, Not statedDec 20361 GW
- Equinor Celtic Sea 1EQUINOR NEW ENERGY LIMITED, Offshore wind, Gate 1Dec 20361 GW