Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Waltham Cross BESS

ENSO GREEN HOLDINGS LIMITED at Waltham Cross 400kV Substation

Connection date
Left 27 Jun 2025
Gate
Not stated
Status
Scoping
Technology
Storage + Solar
Total capacity
57 MW
Connected now
0 MW
Still to connect
57 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-002070
In the register since
May 2023

What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?

Read our analysis: The battery queue and CMP470’s commitment fee

Read our analysis: Delays and exits in the transmission queue since 2021

Read our analysis: Do projects connect on time?

Change history

Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.

  • 27 Jun 2025 register
    Left the register (57 MW from 29 Sep 2028)
  • 31 Jan 2025 register
    Substation name updated in the register (from Waltham Cross GSP to Waltham Cross 400kV Substation)
  • 28 Jul 2023 register
    Capacity changed from 700 MW to 57 MW
  • 28 Jul 2023 register
    Connection date moved from 31 Oct 2029 to 29 Sep 2028 (−13 months)
  • 30 May 2023 register
    Added to the register

Also at Waltham Cross 400kV Substation

Substation view

1 other project, 200 MW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO