Waltham Cross BESS
ENSO GREEN HOLDINGS LIMITED at Waltham Cross 400kV Substation
- Connection date
- Left 27 Jun 2025
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002070
- In the register since
- May 2023
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 27 Jun 2025 registerLeft the register (57 MW from 29 Sep 2028)
- 31 Jan 2025 registerSubstation name updated in the register (from Waltham Cross GSP to Waltham Cross 400kV Substation)
- 28 Jul 2023 registerCapacity changed from 700 MW to 57 MW
- 28 Jul 2023 registerConnection date moved from 31 Oct 2029 to 29 Sep 2028 (−13 months)
- 30 May 2023 registerAdded to the register
Also at Waltham Cross 400kV Substation
Substation view1 other project, 200 MW still to connect at this substation in total.