South Brook
- Connection date
- 28 Jun 2037
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Storage + Solar
- Total capacity
- 35.5 MW
- Connected now
- 0 MW
- Still to connect
- 35.5 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002402
- In the register since
- April 2023
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 28 Mar 2025 registerCustomer changed from DALIA HOLDINGS LTD to JBM SOLAR LIMITED
- 30 May 2023 registerCustomer changed from JBM SOLAR PROJECTS (UK) LTD to DALIA HOLDINGS LTD
- 28 Apr 2023 registerAdded to the register
Also at Melksham 400kV Substation
Substation view5 other projects, 1.9 GW still to connect at this substation in total. 607 MW is due to connect here before this project’s connection date of 28 Jun 2037.
- Melksham (Tertiary)MELKSHAM CALNE GREEN LIMITED, Storage with solar or wind, Not statedJun 202657 MW
- JBM Solar 13 - MelkshamJBM SOLAR PROJECTS 13 LIMITED, Storage with solar or wind, Not statedJul 202649.9 MW
- MelkshamLIME DOWN SOLAR PARK LIMITED, Storage with solar or wind, Not statedJul 2030500 MW
- Melksham BESS & PVELEMENTS GREEN LIMITED, Storage with solar or wind, Not statedOct 2037800 MW
- Melkshem (Cartridge Farm)Queequeg Renewables Ltd, Storage, Not statedOct 2037480 MW