EcoWymondley
Econergy International Limited at Wymondley 2 400kV Substation
- Connection date
- 31 Oct 2033
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Demand + Storage + Solar
- Total capacity
- 249 MW
- Connected now
- 0 MW
- Still to connect
- 249 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002529
- In the register since
- June 2023
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 30 Oct 2033 to 31 Oct 2033 (1 day later)
- 23 Dec 2025 registerMarked as Gate 1
- 16 Dec 2025 registerGate marking removed (was Gate 1)
- 9 Dec 2025 registerMarked as Gate 1
- 29 Jul 2025 registerTechnology changed from Storage, Solar to Demand, Storage, Solar
- 28 Jun 2024 registerConnection point changed from Wymondley 400kV Substation to Wymondley 2 400kV Substation
- 30 Jun 2023 registerAdded to the register
Also at Wymondley 2 400kV Substation
Substation view1 other project, 949 MW still to connect at this substation in total. 700 MW is due to connect here before this project’s connection date of 31 Oct 2033.