Spennymoor GSP
- Connection date
- Left 30 May 2025
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 139 MW
- Connected now
- 0 MW
- Still to connect
- 139 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002970
- In the register since
- April 2025
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 30 May 2025 registerLeft the register (139 MW from 30 Oct 2035)
- 29 Apr 2025 registerAdded to the register
Also at Spennymoor GSP
Substation viewNo other projects in the register at this connection point.