- Connection date
- 30 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003405
- In the register since
- August 2023
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 13 Nov 2026 registerConnection date moved from 31 Oct 2034 to 30 Oct 2034 (1 day earlier)
- 13 Nov 2026 registerMarked as Gate 1
- 27 Sep 2024 registerConnection point changed from Stoke Bardolph 400kV Substation to Trent Valley South Connection Node D 400kV Substation
- 27 Sep 2024 registerConnection date moved from 31 Oct 2032 to 31 Oct 2034 (+24 months)
- 27 Feb 2024 registerCustomer changed from ORRÖN ENERGY DEVELOPMENT LIMITED to Stoke Bardolph 10 Renewables Limited
- 29 Aug 2023 registerAdded to the register
Also at Trent Valley South Connection Node D 400kV Substation
Substation view3 other projects, 6.4 GW still to connect at this substation in total.