- Connection date
- 31 Jul 2032
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 600 MW
- Connected now
- 0 MW
- Still to connect
- 600 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003429
- In the register since
- March 2023
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 9 Dec 2025 registerMarked as Gate 1
- 28 Mar 2025 registerTechnology changed from Storage, Solar to Storage
- 31 Mar 2023 registerAdded to the register
Also at Market Harborough 400kV Substation
Substation view3 other projects, 2.1 GW still to connect at this substation in total. 500 MW is due to connect here before this project’s connection date of 31 Jul 2032.
- Braybrooke Solar and Battery ConnectionIrena BESS LIMITED, Storage with solar or wind, Gate 1Oct 2031500 MW
- Market Harborough GEC (Ethos Green)MARKET HARBOROUGH GREEN ENERGY CENTRE LTD, Storage with solar or wind, Gate 1Oct 2032560 MW
- ER MKH EnergyER PROJECT DEVELOPMENT CO LIMITED, Storage with solar or wind, Gate 1Oct 2033400 MW