- Connection date
- 30 Oct 2037 +24 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Planning consent
- Refused 22 Dec 2025
South Staffordshire, reference 24/01102/FULM · Source: REPD - Technology
- Storage
- Total capacity
- 100 MW
- Connected now
- 0 MW
- Still to connect
- 100 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-003762
- In the register since
- March 2024
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 31 Oct 2035 to 30 Oct 2037 (+24 months)
- 5 Jun 2026 registerConnection point changed from Penn 132kV Substation to Staffordshire Connection Node B 132kV Substation
- 5 Jun 2026 registerMarked as Gate 1
- 26 Mar 2024 registerAdded to the register
Also at Staffordshire Connection Node B 132kV Substation
Substation view1 other project, 250 MW still to connect at this substation in total.