Airtnoch BESS
TURBINE MARKETING SPV LIMITED at Whitelee Extension 275/33kV
- Connection date
- 29 Sep 2027
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Storage
- Total capacity
- 89 MW
- Connected now
- 0 MW
- Still to connect
- 89 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-003769
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 19 Jun 2026 registerMarked as Gate 1
- 29 Aug 2025 registerAgreement type changed from Embedded to Direct Connection
- 27 Sep 2024 registerRenamed from Lochgoin Solar Farm
- 27 Sep 2024 registerSubstation name updated in the register (from Whitelee Extension to Whitelee Extension 275/33kV)
- 27 Sep 2024 registerConnection date moved from 1 Aug 2024 to 29 Sep 2027 (+38 months)
- 27 Sep 2024 registerStatus changed from Scoping to Awaiting Consents
- 27 Sep 2024 registerAgreement type changed from Direct Connection to Embedded
- 27 Sep 2024 registerTechnology changed from Solar to Storage
- 30 Jul 2021 registerConnection date moved from 25 Aug 2023 to 1 Aug 2024 (+11 months)
Also at Whitelee Extension 275/33kV
Substation view1 other project, 121 MW still to connect at this substation in total. 32 MW is due to connect here before this project’s connection date of 29 Sep 2027.