TH Knaresborough
FRV Powertek Limited at Leeds North Connection Node A 400kV Substation
- Connection date
- 30 Oct 2036
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004131
- In the register since
- December 2023
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 13 Nov 2026 registerMarked as Gate 1
- 29 Jul 2025 registerCustomer changed from FRV TH Powertek Limited to FRV Powertek Limited
- 27 Sep 2024 registerConnection point changed from Knaresborough 275kV Substation to Leeds North Connection Node A 400kV Substation
- 27 Sep 2024 registerConnection date moved from 31 Oct 2036 to 30 Oct 2036 (1 day earlier)
- 29 Dec 2023 registerAdded to the register
Also at Leeds North Connection Node A 400kV Substation
Substation viewNo other projects in the register at this connection point.