White Cairns BESS
- Connection date
- Left 28 Nov 2025
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-004219
- In the register since
- September 2023
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 28 Nov 2025 registerLeft the register (400 MW from 31 Oct 2033)
- 30 Jan 2024 registerCustomer changed from CENTRICA BRIGG LIMITED to CBS ENERGY STORAGE ASSETS UK LIMITED
- 29 Sep 2023 registerAdded to the register
Also at Peterhead 275kV
Substation view1 other project, 910 MW still to connect at this substation in total.