Brunt Hill Wind Farm
- Connection date
- 31 Oct 2031
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Storage + Onshore wind
- Total capacity
- 99 MW
- Connected now
- 0 MW
- Still to connect
- 99 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-004322
- In the register since
- May 2025
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 13 Oct 2026 registerTransmission owner changed from SPT to SHET
- 1 Oct 2026 registerTransmission owner changed from SHET to SPT
- 18 Sep 2026 registerStatus changed from Scoping to Awaiting Consents
- 16 Dec 2025 registerTransmission owner changed from SPT to SHET
- 31 Oct 2025 registerConnection date moved from 31 Oct 2032 to 31 Oct 2031 (−12 months)
- 30 May 2025 registerAdded to the register
Also at Westfield 132/33kV
Substation view2 other projects, 1.2 GW still to connect at this substation in total.