Hockliffe GEC (Ethos Green)
HOCKLIFFE GREEN ENERGY CENTRE LTD at Dunstable 400kV Substation
- Connection date
- 29 Oct 2032
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 850 MW
- Connected now
- 0 MW
- Still to connect
- 850 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004342
- In the register since
- October 2023
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 20 Oct 2026 registerMarked as Gate 1
- 7 Aug 2026 registerTechnology changed from Demand, Storage, Solar, Reactive compensation to Storage, Solar
- 31 Oct 2023 registerAdded to the register
Also at Dunstable 400kV Substation
Substation view2 other projects, 1.9 GW still to connect at this substation in total. 840 MW is due to connect here before this project’s connection date of 29 Oct 2032.