Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Bearsden BESS

BEARSDEN BESS LTD at BEARSDEN BESS 275KV SUBSTATION

Connection date
Left 13 Nov 2026
Gate
Gate 1
Status
Scoping
Technology
Storage
Total capacity
240 MW
Connected now
0 MW
Still to connect
240 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-004404
In the register since
November 2023

What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?

Read our analysis: The battery queue and CMP470’s commitment fee

Read our analysis: Delays and exits in the transmission queue since 2021

Read our analysis: Do projects connect on time?

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
1010010031 Oct 2029Gate 1Scoping
2014024031 Oct 2033Gate 1Scoping

Change history

Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.

  • 13 Nov 2026 register
    Left the register (100 MW from 31 Oct 2029, 140 MW from 31 Oct 2033)
  • 3 Nov 2026 register
    Stage 2: 100 MW no longer connected
  • 10 Oct 2026 register
    Listed again
  • 14 Aug 2026 register
    Not in this register
  • 16 Jun 2026 register
    Connection point changed from Windyhill 275kV Substation to BEARSDEN BESS 275KV SUBSTATION
  • 20 Mar 2026 register
    Stage 1: Marked as Gate 1
  • 20 Mar 2026 register
    Stage 2: Marked as Gate 1
  • 28 Mar 2025 register
    Connection point changed from Windyhill 275/132kV to Windyhill 275kV Substation
  • 29 Oct 2024 register
    Restructured from 1 stage (100 MW from 31 Oct 2028) to 2 stages (100 MW from 31 Oct 2029, 140 MW from 31 Oct 2033). First connection date +12 months
  • 27 Sep 2024 register
    Connection point changed from Windy Hill Grid 132kV Substation to Windyhill 275/132kV
  • 28 Nov 2023 register
    Added to the register

Also at BEARSDEN BESS 275KV SUBSTATION

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO