West Botley High Impact Green Energy Hub
- Connection date
- 31 Oct 2037
- Gate
- Not stated
- Status
- Scoping
- Technology
- Demand + Storage + Nuclear + Solar + Onshore wind
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004435
- In the register since
- January 2025
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 13 Nov 2026 registerCapacity changed from 100 MW to 1,000 MW
- 31 Jan 2025 registerAdded to the register
Also at Botley West 400kV Substation
Substation view1 other project, 1.3 GW still to connect at this substation in total. 280 MW is due to connect here before this project’s connection date of 31 Oct 2037.