Wick Moor Drove
BSR APPLICATIONS LIMITED at West Country Connection Node D 400kV Substation
- Connection date
- 31 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar + Onshore wind
- Total capacity
- 500 MW
- Connected now
- 0 MW
- Still to connect
- 500 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004788
- In the register since
- February 2025
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 13 Nov 2026 registerMarked as Gate 1
- 28 Feb 2025 registerAdded to the register
Also at West Country Connection Node D 400kV Substation
Substation view1 other project, 700 MW still to connect at this substation in total.